IAC Assessment: UD0726
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UD0726
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Dayton
Assessment Year 2005
Principal Product Aluminum and zinc die castings
NAICS 331523 - Nonferrous Metal Die-Casting Foundries
SIC 3363 - Aluminum Die-castings
Sales $10,000,000-$50,000,000
# of Employees 208
Plant Area (Sq.Ft.) 200,000
Annual Production 21,000,000 Pieces
Production Hrs. Annual 4,050
Location (State) OH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $332,851 8,938,455 kWh $0.04
Electricity Demand $396,931 22,596 kW-months/year $17.57
Natural Gas $1,110,171 118,841 MMBtu $9.34
TOTAL ENERGY COSTS $1,895,802
RECOMMENDED SAVINGS* $722,726 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $410,599
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Natural Gas Ancillary Material Cost Electricity Usage Electricity Demand Electricity Fees Natural Gas Ancillary Material Cost
$ kWh $ kW-months/year $ $ $ MMBtu $ $
01: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$222,216
Cost:
$3,730
- - - - - - $222,216 26,143 - - -
-
kWh
-
-
kW-months/year
-
-
$
$222,216
26,143
MMBtu
-
-
$
02: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$157,981
Cost:
$295,540
- - - - - - $157,981 18,586 - - -
-
kWh
-
-
kW-months/year
-
-
$
$157,981
18,586
MMBtu
-
-
$
03: 2.2515 USE OPTIMUM THICKNESS INSULATION Savings:
$113,135
Cost:
$17,165
- - - - - - $113,135 13,310 - - -
-
kWh
-
-
kW-months/year
-
-
$
$113,135
13,310
MMBtu
-
-
$
04: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$93,662
Cost:
$72,100
- - - - - - $93,662 11,019 - - -
-
kWh
-
-
kW-months/year
-
-
$
$93,662
11,019
MMBtu
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$27,707
Cost:
$93,840
$7,764 287,064 $18,422 852 - - - - $1,521 - $7,764
287,064
kWh
$18,422
852
kW-months/year
-
-
$
-
-
MMBtu
$1,521
-
$
06: 2.7314 REDUCE VENTILATION AIR Savings:
$26,800
Cost:
-
- - - - - - $26,800 3,162 - - -
-
kWh
-
-
kW-months/year
-
-
$
$26,800
3,162
MMBtu
-
-
$
07: 2.2511 INSULATE BARE EQUIPMENT Savings:
$19,788
Cost:
$4,000
- - - - - - $19,788 2,328 - - -
-
kWh
-
-
kW-months/year
-
-
$
$19,788
2,328
MMBtu
-
-
$
08: 2.2424 USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS Savings:
$19,593
Cost:
$40,000
- - - - - - $19,593 2,305 - - -
-
kWh
-
-
kW-months/year
-
-
$
$19,593
2,305
MMBtu
-
-
$
09: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$19,470
Cost:
$3,940
$6,470 239,600 $13,000 600 - - - - - - $6,470
239,600
kWh
$13,000
600
kW-months/year
-
-
$
-
-
MMBtu
-
-
$
10: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$4,819
Cost:
$12,560
$4,819 58,767 - - - - - - - - $4,819
58,767
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
$
11: 2.2514 COVER OPEN TANKS Savings:
$4,429
Cost:
$1,200
- - - - - - $4,429 521 - - -
-
kWh
-
-
kW-months/year
-
-
$
$4,429
521
MMBtu
-
-
$
12: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$4,280
Cost:
$736
$292 10,800 $520 24 - - $3,468 408 - - $292
10,800
kWh
$520
24
kW-months/year
-
-
$
$3,468
408
MMBtu
-
-
$
13: 2.4224 UPGRADE CONTROLS ON COMPRESSORS Savings:
$3,679
Cost:
-
$1,338 49,572 $2,341 108 - - - - - - $1,338
49,572
kWh
$2,341
108
kW-months/year
-
-
$
-
-
MMBtu
-
-
$
14: 2.4131 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY Savings:
$1,948
Cost:
$500
$648 24,000 $1,300 60 - - - - - - $648
24,000
kWh
$1,300
60
kW-months/year
-
-
$
-
-
MMBtu
-
-
$
15: 2.8118 CHECK FOR ACCURACY OF UTILITY / POWER METERS Savings:
$1,554
Cost:
-
- - - - $1,554 - - - - - -
-
kWh
-
-
kW-months/year
$1,554
-
$
-
-
MMBtu
-
-
$
16: 2.4224 UPGRADE CONTROLS ON COMPRESSORS Savings:
$1,253
Cost:
-
$1,253 46,400 - - - - - - - - $1,253
46,400
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
$
17: 2.7121 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT Savings:
$412
Cost:
$960
$412 15,245 - - - - - - - - $412
15,245
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$722,726
Cost:
$546,271
$22,996 731,448 $35,583 1,644 $1,554 - $661,072 77,782 $1,521 - $22,996
731,448
kWh
$35,583
1,644
kW-months/year
$1,554
-
$
$661,072
77,782
MMBtu
$1,521
-
$
TOTAL IMPLEMENTED Savings:
$410,599
Cost:
$189,126
$15,878 467,848 $21,283 984 $1,554 - $370,363 43,581 $1,521 - $15,878
467,848
kWh
$21,283
984
kW-months/year
$1,554
-
$
$370,363
43,581
MMBtu
$1,521
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ MMBtu $ $
Electricity Usage Electricity Demand Electricity Fees Natural Gas Ancillary Material Cost Electricity Usage Electricity Demand Electricity Fees Natural Gas Ancillary Material Cost