Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 2007 |
Principal Product | Resin and Latex |
NAICS | 325211 - Plastics Material and Resin Manufacturing |
SIC | 2821 - Plastics Materials And Resins |
Sales | $10,000,000-$50,000,000 |
# of Employees | 50 |
Plant Area (Sq.Ft.) | 112,000 |
Annual Production | 22,000,000 Pounds |
Production Hrs. Annual | 8,400 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $368,548 | 6,997,734 | kWh | $0.05 |
Other Energy | $653,420 | 82,042 | MMBtu | $7.96 |
TOTAL ENERGY COSTS | $1,112,754 | |||
RECOMMENDED SAVINGS* | $321,859 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $173,048 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Other Energy | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Other Energy | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2223 ENHANCE SENSITIVITY OF TEMPERATURE CONTROL AND CUTOFF |
Savings: $73,500 Cost: $147,000 |
- | - | - | - | - | - | $73,500 | 6,125 | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$73,500 6,125 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $57,728 Cost: $10,396 |
$36,288 | 362,880 | - | - | - | - | - | - | $21,440 | - |
$36,288 362,880 kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
$21,440 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3415 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT |
Savings: $49,140 Cost: $253,091 |
$109,200 | 1,902,000 | - | - | $(-141,456) | 14,146 | $97,776 | 8,148 | $(-16,380) | - |
$109,200 1,902,000 kWh |
- - kW-months/year |
$(-141,456) 14,146 MMBtu |
$97,776 8,148 MMBtu |
$(-16,380) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3411 REPLACE ELECTRIC MOTORS WITH BACK PRESSURE STEAM TURBINES AND USE EXHAUST STEAM FOR PROCESS HEAT |
Savings: $46,585 Cost: $42,000 |
$46,585 | 465,847 | - | - | - | - | - | - | - | - |
$46,585 465,847 kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.3415 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT |
Savings: $33,617 Cost: $337,437 |
$109,200 | 1,902,000 | - | - | $(-141,456) | (-14,146) | $82,253 | 6,854 | $(-16,380) | - |
$109,200 1,902,000 kWh |
- - kW-months/year |
$(-141,456) (-14,146) MMBtu |
$82,253 6,854 MMBtu |
$(-16,380) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $14,952 Cost: $19,500 |
$14,553 | 145,530 | - | - | - | - | - | - | $399 | - |
$14,553 145,530 kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
$399 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $12,600 Cost: $15,000 |
$12,600 | 126,000 | - | - | - | - | - | - | - | - |
$12,600 126,000 kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.3137 USE POWER DURING OFF-PEAK PERIODS |
Savings: $12,404 Cost: - |
- | - | $12,404 | - | - | - | - | - | - | - |
- - kWh |
$12,404 - kW-months/year |
- - MMBtu |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $11,340 Cost: $2,000 |
- | - | - | - | - | - | $11,340 | 1,945 | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$11,340 1,945 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.2515 USE OPTIMUM THICKNESS INSULATION |
Savings: $4,545 Cost: $16,005 |
- | - | - | - | - | - | $4,545 | 379 | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$4,545 379 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $2,520 Cost: - |
$2,520 | 25,200 | - | - | - | - | - | - | - | - |
$2,520 25,200 kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.7491 INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS |
Savings: $2,928 Cost: $42,500 |
- | - | - | - | - | - | $2,928 | 244 | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$2,928 244 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $321,859 Cost: $884,929 |
$330,946 | 4,929,457 | $12,404 | - | $(-282,912) | - | $272,342 | 23,695 | $(-10,921) | - | $330,946 4,929,457 kWh |
$12,404 - kW-months/year |
$(-282,912) - MMBtu |
$272,342 23,695 MMBtu |
$(-10,921) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $173,048 Cost: $236,396 |
$63,441 | 634,410 | - | - | - | - | $87,768 | 8,314 | $21,839 | - | $63,441 634,410 kWh |
- - kW-months/year |
- - MMBtu |
$87,768 8,314 MMBtu |
$21,839 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Other Energy | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Other Energy | Administrative Changes |