IAC Assessment: UD0994
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UD0994
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Dayton
Assessment Year 2019
Principal Product Automotive Sealing Systems
NAICS 326299 - All Other Rubber Product Manufacturing
SIC 3069 - Fabricated Rubber Products, Nec
Sales $50,000,000-$100,000,000
# of Employees 256
Plant Area (Sq.Ft.) 273,000
Annual Production 53,000,000 Units
Production Hrs. Annual 7,000
Location (State) OH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $606,999 9,379,800 kWh $0.06
Electricity Demand $342,643 22,361 kW-months/year $15.32
Electricity Fees $12,982 - $ -
Natural Gas $197,938 41,621 MMBtu $4.76
TOTAL ENERGY COSTS $1,202,928
RECOMMENDED SAVINGS* $410,261 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $248,034
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Water Disposal Administrative Changes Electricity Usage Electricity Demand Natural Gas Water Disposal Administrative Changes
$ kWh $ kW-months/year $ MMBtu $ Tgal $ $
01: 2.3134 SHIFT FROM DAYTIME TO NIGHTTIME OPERATION Savings:
$100,170
Cost:
-
- - $100,170 6,360 - - - - - - -
-
kWh
$100,170
6,360
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
02: 3.4116 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) Savings:
$5,091
Cost:
$700
- - - - - - $5,091 1,437 - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$5,091
1,437
Tgal
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$46,649
Cost:
$33,788
$31,073 494,482 $15,576 989 - - - - - - $31,073
494,482
kWh
$15,576
989
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
04: 2.2449 RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER Savings:
$248,034
Cost:
$337,264
$74,023 1,117,965 $61,796 3,924 $51,315 10,780 - - $60,900 - $74,023
1,117,965
kWh
$61,796
3,924
kW-months/year
$51,315
10,780
MMBtu
-
-
Tgal
$60,900
-
$
05: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$6,349
Cost:
$10,250
$6,349 101,034 - - - - - - - - $6,349
101,034
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$3,968
Cost:
$8,550
$3,968 63,595 - - - - - - - - $3,968
63,595
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
TOTAL RECOMMENDED Savings:
$410,261
Cost:
$390,552
$115,413 1,777,076 $177,542 11,273 $51,315 10,780 $5,091 1,437 $60,900 - $115,413
1,777,076
kWh
$177,542
11,273
kW-months/year
$51,315
10,780
MMBtu
$5,091
1,437
Tgal
$60,900
-
$
TOTAL IMPLEMENTED Savings:
$248,034
Cost:
$337,264
$74,023 1,117,965 $61,796 3,924 $51,315 10,780 - - $60,900 - $74,023
1,117,965
kWh
$61,796
3,924
kW-months/year
$51,315
10,780
MMBtu
-
-
Tgal
$60,900
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ Tgal $ $
Electricity Usage Electricity Demand Natural Gas Water Disposal Administrative Changes Electricity Usage Electricity Demand Natural Gas Water Disposal Administrative Changes