IAC logo
IAC Assessment: UD1072
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UD1072
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Dayton
Assessment Year 2024
Principal Product Fabricated rubber Products, Not Elsewhere Classified
NAICS 326299 - All Other Rubber Product Manufacturing
SIC 3069 - Fabricated Rubber Products, Nec
Sales $50,000,000-$100,000,000
# of Employees 110
Plant Area (Sq.Ft.) 775,000
Annual Production 240,000,000 Pounds
Production Hrs. Annual 6,000
Location (State) OH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $485,719 6,730,720 kWh $0.07
Electricity Demand $152,235 21,717 kW-months/year $7.01
Natural Gas $553,772 124,152 MMBtu $4.46
TOTAL ENERGY COSTS $1,191,726
RECOMMENDED SAVINGS* $32,366 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Personnel Changes Ancillary Material Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $
01: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$5,741
Cost:
-
$5,741 79,511 - - - - - - - - $5,741
79,511
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
02: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$3,199
Cost:
$864
- - - - $3,199 609 - - - - -
-
kWh
-
-
kW-months/year
$3,199
609
MMBtu
-
-
$
-
-
$
03: 2.2122 INSTALL / REPAIR INSULATION ON CONDENSATE LINES Savings:
$63
Cost:
$216
- - - - $63 12 - - - - -
-
kWh
-
-
kW-months/year
$63
12
MMBtu
-
-
$
-
-
$
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$2,454
Cost:
$952
$2,149 29,765 $305 44 - - - - - - $2,149
29,765
kWh
$305
44
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$4,892
Cost:
$12,650
$4,646 64,350 $902 128 - - $(-656) - - - $4,646
64,350
kWh
$902
128
kW-months/year
-
-
MMBtu
$(-656)
-
$
-
-
$
06: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$1,343
Cost:
$1,667
$1,219 16,884 - - - - $3 - $121 - $1,219
16,884
kWh
-
-
kW-months/year
-
-
MMBtu
$3
-
$
$121
-
$
07: 2.3413 BURN FOSSIL FUEL TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR AND USE STEAM EXHAUST FOR HEAT Savings:
$14,674
Cost:
$67,830
$25,121 347,933 $3,341 477 $(-13,788) (-3,092) - - - - $25,121
347,933
kWh
$3,341
477
kW-months/year
$(-13,788)
(-3,092)
MMBtu
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$32,366
Cost:
$84,179
$38,876 538,443 $4,548 649 $(-10,526) (-2,471) $(-653) - $121 - $38,876
538,443
kWh
$4,548
649
kW-months/year
$(-10,526)
(-2,471)
MMBtu
$(-653)
-
$
$121
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $
Electricity Usage Electricity Demand Natural Gas Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Personnel Changes Ancillary Material Cost