Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 2025 |
Principal Product | Wood Shavings, Wood Flour, Pet Bedding |
NAICS | 321219 - Reconstituted Wood Product Manufacturing |
SIC | 2493 - Reconstituted Wood Products |
Sales | $10,000,000-$50,000,000 |
# of Employees | 37 |
Plant Area (Sq.Ft.) | 90,000 |
Annual Production | 78,924 Tons |
Production Hrs. Annual | 7,488 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $958,922 | 13,238,400 | kWh | $0.07 |
Electricity Demand | $190,891 | 30,157 | kW-months/year | $6.33 |
Electricity Fees | $24,347 | - | $ | - |
Natural Gas | $14,882 | 1,178 | MMBtu | $12.63 |
TOTAL ENERGY COSTS | $1,199,297 | |||
RECOMMENDED SAVINGS* | $302,555 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Personnel Changes | Ancillary Material Cost | Increase in Production | Electricity Usage | Electricity Demand | Electricity Fees | Personnel Changes | Ancillary Material Cost | Increase in Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | $ | % | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $228,685 Cost: $136,500 |
- | - | - | - | $22,685 | - | - | - | - | - | $206,000 | - |
- - kWh |
- - kW-months/year |
$22,685 - $ |
- - $ |
- - $ |
$206,000 - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $69,274 Cost: - |
- | - | $69,274 | 10,960 | - | - | - | - | - | - | - | - |
- - kWh |
$69,274 10,960 kW-months/year |
- - $ |
- - $ |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,345 Cost: $953 |
$1,180 | 16,293 | $165 | 26 | - | - | - | - | - | - | - | - |
$1,180 16,293 kWh |
$165 26 kW-months/year |
- - $ |
- - $ |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $412 Cost: $900 |
$345 | 4,761 | $67 | 11 | - | - | - | - | - | - | - | - |
$345 4,761 kWh |
$67 11 kW-months/year |
- - $ |
- - $ |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,839 Cost: $5,280 |
$1,433 | 19,788 | $201 | 32 | - | - | $1,095 | - | $110 | - | - | - |
$1,433 19,788 kWh |
$201 32 kW-months/year |
- - $ |
$1,095 - $ |
$110 - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $302,555 Cost: $143,633 |
$2,958 | 40,842 | $69,707 | 11,029 | $22,685 | - | $1,095 | - | $110 | - | $206,000 | - | $2,958 40,842 kWh |
$69,707 11,029 kW-months/year |
$22,685 - $ |
$1,095 - $ |
$110 - $ |
$206,000 - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - $ |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | $ | % | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Personnel Changes | Ancillary Material Cost | Increase in Production | Electricity Usage | Electricity Demand | Electricity Fees | Personnel Changes | Ancillary Material Cost | Increase in Production |