Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Florida |
---|---|
Assessment Year | 1992 |
Principal Product | PRE-STRESSED CONCRETE |
NAICS | n/a |
SIC | 3449 - Miscellaneous Metal Work |
Sales | $10,000,000-$50,000,000 |
# of Employees | 35 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 20,000 Tons |
Production Hrs. Annual | 7,488 |
Location (State) | FL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,086,952 | 17,549,238 | kWh | $0.06 |
LPG | $23,435 | 3,774 | MMBtu | $6.21 |
Other Energy | $3,187 | 503 | MMBtu | $6.34 |
TOTAL ENERGY COSTS | $1,113,574 | |||
RECOMMENDED SAVINGS* | $13,866 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $13,866 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Usage | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $864 Cost: $2,517 |
$864 | 14,068 |
$864 14,068 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7144 INSTALL SPECTRAL REFLECTORS / DELAMP |
Savings: $6,437 Cost: $2,400 |
$6,437 | 103,751 |
$6,437 103,751 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7233 USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT |
Savings: $1,125 Cost: $1,660 |
$1,125 | 18,171 |
$1,125 18,171 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $5,440 Cost: $36,148 |
$5,440 | 87,632 |
$5,440 87,632 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $13,866 Cost: $42,725 |
$13,866 | 223,622 | $13,866 223,622 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $13,866 Cost: $42,725 |
$13,866 | 223,622 | $13,866 223,622 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Usage |