Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Florida |
---|---|
Assessment Year | 1993 |
Principal Product | POLYYURETHANE FOAM |
NAICS | n/a |
SIC | 3086 - Plastics Foam Products |
Sales | $500,000-$1,000,000 |
# of Employees | 120 |
Plant Area (Sq.Ft.) | 175,000 |
Annual Production | 124,000 Thousand Feet |
Production Hrs. Annual | 5,460 |
Location (State) | FL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $202,701 | 3,305,393 | kWh | $0.06 |
Natural Gas | $42,562 | 7,197 | MMBtu | $5.91 |
TOTAL ENERGY COSTS | $245,263 | |||
RECOMMENDED SAVINGS* | $62,993 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $16,285 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $5,736 Cost: $17,345 |
$5,736 | 94,080 | - | - |
$5,736 94,080 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $21,182 Cost: $1,060 |
$21,182 | 347,304 | - | - |
$21,182 347,304 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $18,545 Cost: $5,513 |
$18,545 | 303,927 | - | - |
$18,545 303,927 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $431 Cost: $391 |
$431 | 7,034 | - | - |
$431 7,034 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $1,347 Cost: $1,000 |
- | - | $1,347 | 228 |
- - kWh |
$1,347 228 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $10,938 Cost: $20,958 |
$10,938 | 179,367 | - | - |
$10,938 179,367 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,816 Cost: $1,000 |
$2,816 | 46,307 | - | - |
$2,816 46,307 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $236 Cost: $500 |
$236 | 3,810 | - | - |
$236 3,810 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL |
Savings: $488 Cost: $2,000 |
$488 | 7,913 | - | - |
$488 7,913 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7492 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE |
Savings: $814 Cost: $1,392 |
$814 | 13,482 | - | - |
$814 13,482 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $460 Cost: $407 |
- | - | $460 | 78 |
- - kWh |
$460 78 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $62,993 Cost: $51,566 |
$61,186 | 1,003,224 | $1,807 | 306 | $61,186 1,003,224 kWh |
$1,807 306 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $16,285 Cost: $25,865 |
$14,478 | 237,397 | $1,807 | 306 | $14,478 237,397 kWh |
$1,807 306 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |