IAC Assessment: UF0183
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UF0183
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Florida
Assessment Year 1997
Principal Product Steel Wire Mesh
NAICS n/a
SIC 3496 - Misc. Fabricated Wire Products
Sales $10,000,000-$50,000,000
# of Employees 160
Plant Area (Sq.Ft.) 200,000
Annual Production 60,000 Tons
Production Hrs. Annual 7,344
Location (State) FL
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $222,494 5,738,570 kWh $0.04
Electricity Demand $133,729 14,899 kW-months/year $8.98
TOTAL ENERGY COSTS $380,223
RECOMMENDED SAVINGS* $111,404 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $9,468
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Solid Waste (non-haz) Administrative Changes Primary Raw Material Electricity Usage Electricity Demand Solid Waste (non-haz) Administrative Changes Primary Raw Material
$ kWh $ kW-months/year $ lb $ $ $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,839
Cost:
$1,956
$2,031 53,341 $808 90 - - - - - - $2,031
53,341
kWh
$808
90
kW-months/year
-
-
lb
-
-
$
-
-
$
02: 2.7134 USE PHOTOCELL CONTROLS Savings:
$1,078
Cost:
$1,100
$1,078 28,429 - - - - - - - - $1,078
28,429
kWh
-
-
kW-months/year
-
-
lb
-
-
$
-
-
$
03: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$1,073
Cost:
$1,913
$634 16,706 $439 49 - - - - - - $634
16,706
kWh
$439
49
kW-months/year
-
-
lb
-
-
$
-
-
$
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$5,556
Cost:
$1,850
$5,556 146,249 - - - - - - - - $5,556
146,249
kWh
-
-
kW-months/year
-
-
lb
-
-
$
-
-
$
05: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR Savings:
$1,573
Cost:
-
- - $1,573 175 - - - - - - -
-
kWh
$1,573
175
kW-months/year
-
-
lb
-
-
$
-
-
$
06: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$9,095
Cost:
$36,500
- - - - - - $9,095 - - - -
-
kWh
-
-
kW-months/year
-
-
lb
$9,095
-
$
-
-
$
07: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES Savings:
$58,776
Cost:
-
- - - - $7,347 368,000 - - $51,429 - -
-
kWh
-
-
kW-months/year
$7,347
368,000
lb
-
-
$
$51,429
-
$
08: 3.7121 IMPROVE HANDLING PRACTICES Savings:
$12,852
Cost:
$6,000
- - - - - - $12,852 - - - -
-
kWh
-
-
kW-months/year
-
-
lb
$12,852
-
$
-
-
$
09: 4.321 OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES Savings:
$18,562
Cost:
$8,530
- - - - - - $18,562 - - - -
-
kWh
-
-
kW-months/year
-
-
lb
$18,562
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$111,404
Cost:
$57,849
$9,299 244,725 $2,820 314 $7,347 368,000 $40,509 - $51,429 - $9,299
244,725
kWh
$2,820
314
kW-months/year
$7,347
368,000
lb
$40,509
-
$
$51,429
-
$
TOTAL IMPLEMENTED Savings:
$9,468
Cost:
$5,719
$8,221 216,296 $1,247 139 - - - - - - $8,221
216,296
kWh
$1,247
139
kW-months/year
-
-
lb
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ lb $ $ $ $
Electricity Usage Electricity Demand Solid Waste (non-haz) Administrative Changes Primary Raw Material Electricity Usage Electricity Demand Solid Waste (non-haz) Administrative Changes Primary Raw Material