IAC logo
IAC Assessment: UF0249
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UF0249
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Florida
Assessment Year 2000
Principal Product Car Batteries
NAICS n/a
SIC 3691 - Storage Batteries
Sales $50,000,000-$100,000,000
# of Employees 220
Plant Area (Sq.Ft.) 195,000
Annual Production 2,900,000 Pieces
Production Hrs. Annual 4,160
Location (State) FL
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $1,305,153 26,901,231 kWh $0.05
Electricity Demand $85,055 52,884 kW-months/year $1.61
Electricity Fees $449,439 - $ -
Natural Gas $146,707 53,550 MMBtu $2.74
TOTAL ENERGY COSTS $1,986,354
RECOMMENDED SAVINGS* $2,294,730 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $39,257
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Natural Gas Solid Waste (non-haz) Administrative Changes Electricity Usage Electricity Demand Electricity Fees Natural Gas Solid Waste (non-haz) Administrative Changes
$ kWh $ kW-months/year $ $ $ MMBtu $ lb $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$6,575
Cost:
$6,093
$6,008 122,509 $567 1 - - - - - - - - $6,008
122,509
kWh
$567
1
kW-months/year
-
-
$
-
-
MMBtu
-
-
lb
-
-
$
02: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES Savings:
$31,004
Cost:
$50
- - - - - - - - - - $31,004 - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
lb
$31,004
-
$
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$16,950
Cost:
$25,000
- - - - - - $16,950 6,186 - - - - -
-
kWh
-
-
kW-months/year
-
-
$
$16,950
6,186
MMBtu
-
-
lb
-
-
$
04: 2.3417 USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT Savings:
$1,684,933
Cost:
$2,200,000
$1,287,720 26,279,895 $57,960 36,000 - - $285,253 (-104,107) - - $54,000 - $1,287,720
26,279,895
kWh
$57,960
36,000
kW-months/year
-
-
$
$285,253
(-104,107)
MMBtu
-
-
lb
$54,000
-
$
05: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$1,678
Cost:
$4,886
$1,603 32,825 $75 4 - - - - - - - - $1,603
32,825
kWh
$75
4
kW-months/year
-
-
$
-
-
MMBtu
-
-
lb
-
-
$
06: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS Savings:
$93,870
Cost:
$9,000
- - - - - - - - $93,870 - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
$93,870
-
lb
-
-
$
07: 3.5218 REUSE / RECYCLE/ SELL RUBBER PRODUCTS Savings:
$2,400
Cost:
-
- - - - - - - - $2,400 - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
$2,400
-
lb
-
-
$
08: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$7,881
Cost:
$9,000
- - - - - - - - - - $7,881 - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
lb
$7,881
-
$
09: 4.651 INSTALL BACK-UP EQUIPMENT Savings:
$449,439
Cost:
$2,100,000
- - - - $449,439 - - - - - - - -
-
kWh
-
-
kW-months/year
$449,439
-
$
-
-
MMBtu
-
-
lb
-
-
$
TOTAL RECOMMENDED Savings:
$2,294,730
Cost:
$4,354,029
$1,295,331 26,435,229 $58,602 36,005 $449,439 - $302,203 (-97,921) $96,270 - $92,885 - $1,295,331
26,435,229
kWh
$58,602
36,005
kW-months/year
$449,439
-
$
$302,203
(-97,921)
MMBtu
$96,270
-
lb
$92,885
-
$
TOTAL IMPLEMENTED Savings:
$39,257
Cost:
$11,029
$7,611 155,334 $642 5 - - - - - - $31,004 - $7,611
155,334
kWh
$642
5
kW-months/year
-
-
$
-
-
MMBtu
-
-
lb
$31,004
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ MMBtu $ lb $ $
Electricity Usage Electricity Demand Electricity Fees Natural Gas Solid Waste (non-haz) Administrative Changes Electricity Usage Electricity Demand Electricity Fees Natural Gas Solid Waste (non-haz) Administrative Changes