Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Florida |
---|---|
Assessment Year | 2001 |
Principal Product | Process & Tissue Implants, R&D Orthopedic, Prosthetic & Surg |
NAICS | n/a |
SIC | 3842 - Surgical Appliances And Supplies |
Sales | $1,000,000-$5,000,000 |
# of Employees | 370 |
Plant Area (Sq.Ft.) | 63,000 |
Annual Production | 180,733 Pieces |
Production Hrs. Annual | 4,160 |
Location (State) | FL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $333,682 | 5,774,352 | kWh | $0.06 |
Electricity Demand | $68,603 | 11,611 | kW-months/year | $5.91 |
Natural Gas | $43,084 | 4,625 | MMBtu | $9.32 |
TOTAL ENERGY COSTS | $445,369 | |||
RECOMMENDED SAVINGS* | $132,485 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $99,409 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | One-time Revenue or Avoided Cost | Primary Product | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | One-time Revenue or Avoided Cost | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,092 Cost: $920 |
$784 | 13,520 | $308 | 4 | - | - | - | - | - | - | - | - |
$784 13,520 kWh |
$308 4 kW-months/year |
- - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,260 Cost: $2,081 |
$1,260 | 21,715 | - | - | - | - | - | - | - | - | - | - |
$1,260 21,715 kWh |
- - kW-months/year |
- - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,637 Cost: $16,038 |
$2,613 | 45,053 | $1,024 | 14 | - | - | - | - | - | - | - | - |
$2,613 45,053 kWh |
$1,024 14 kW-months/year |
- - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7121 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT |
Savings: $3,729 Cost: $10,788 |
$2,515 | 43,360 | $1,314 | 19 | - | - | $(-100) | - | - | - | - | - |
$2,515 43,360 kWh |
$1,314 19 kW-months/year |
- - $ |
$(-100) - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $28,709 Cost: $20,000 |
$28,709 | 494,983 | - | - | - | - | - | - | - | - | - | - |
$28,709 494,983 kWh |
- - kW-months/year |
- - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $1,358 Cost: - |
$1,344 | 23,179 | $14 | - | - | - | - | - | - | - | - | - |
$1,344 23,179 kWh |
$14 - kW-months/year |
- - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $9,303 Cost: $225 |
$9,303 | 117,754 | - | - | - | - | - | - | - | - | - | - |
$9,303 117,754 kWh |
- - kW-months/year |
- - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 4.448 INSTALL AUTOMATIC PART STORAGE / RETREVAL SYSTEM |
Savings: $39,000 Cost: $5,247 |
- | - | - | - | - | - | - | - | - | - | $39,000 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - $ |
- - $ |
$39,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.8123 PAY UTILITY BILLS ON TIME |
Savings: $15,147 Cost: - |
- | - | - | - | - | - | - | - | $15,147 | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - $ |
$15,147 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS |
Savings: $29,250 Cost: $3,000 |
- | - | - | - | $29,250 | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$29,250 - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $132,485 Cost: $58,299 |
$46,528 | 759,564 | $2,660 | 37 | $29,250 | - | $(-100) | - | $15,147 | - | $39,000 | - | $46,528 759,564 kWh |
$2,660 37 kW-months/year |
$29,250 - $ |
$(-100) - $ |
$15,147 - $ |
$39,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $99,409 Cost: $29,167 |
$30,837 | 531,682 | $322 | 4 | $29,250 | - | - | - | - | - | $39,000 | - | $30,837 531,682 kWh |
$322 4 kW-months/year |
$29,250 - $ |
- - $ |
- - $ |
$39,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | One-time Revenue or Avoided Cost | Primary Product | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | One-time Revenue or Avoided Cost | Primary Product |