Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Florida |
---|---|
Assessment Year | 2019 |
Principal Product | Reclaimed Water and Bio-Solids |
NAICS | 221320 - Sewage Treatment Facilities |
SIC | 4952 - Sewerage Systems |
Sales | $10,000,000-$50,000,000 |
# of Employees | 27 |
Plant Area (Sq.Ft.) | 23,959 |
Annual Production | 3,000,000 Thousand Gallons |
Production Hrs. Annual | 8,760 |
Location (State) | FL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $389,741 | 7,077,600 | kWh | $0.06 |
Electricity Demand | $69,096 | 14,644 | kW-months/year | $4.72 |
Electricity Fees | $8,508 | - | $ | - |
LPG | $42,659 | 1,039 | MMBtu | $41.06 |
TOTAL ENERGY COSTS | $510,004 | |||
RECOMMENDED SAVINGS* | $50,990 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $50,990 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | LPG | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | LPG | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $35,230 Cost: $127,650 |
$25,309 | 460,169 | $9,921 | 2,103 | - | - | - | - | - | - |
$25,309 460,169 kWh |
$9,921 2,103 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $5,527 Cost: - |
$4,838 | 87,971 | - | - | - | - | $350 | - | $339 | - |
$4,838 87,971 kWh |
- - kW-months/year |
- - MMBtu |
$350 - $ |
$339 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $3,486 Cost: $3,283 |
$3,486 | 63,377 | - | - | - | - | - | - | - | - |
$3,486 63,377 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,073 Cost: $2,563 |
$2,627 | 47,771 | $446 | 94 | - | - | - | - | - | - |
$2,627 47,771 kWh |
$446 94 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2427 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT INCOMING FLUIDS |
Savings: $2,330 Cost: $6,000 |
- | - | - | - | $2,330 | 57 | - | - | - | - |
- - kWh |
- - kW-months/year |
$2,330 57 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $1,344 Cost: $1,400 |
- | - | - | - | $1,344 | 33 | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,344 33 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $50,990 Cost: $140,896 |
$36,260 | 659,288 | $10,367 | 2,197 | $3,674 | 89 | $350 | - | $339 | - | $36,260 659,288 kWh |
$10,367 2,197 kW-months/year |
$3,674 89 MMBtu |
$350 - $ |
$339 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $50,990 Cost: $140,896 |
$36,260 | 659,288 | $10,367 | 2,197 | $3,674 | 89 | $350 | - | $339 | - | $36,260 659,288 kWh |
$10,367 2,197 kW-months/year |
$3,674 89 MMBtu |
$350 - $ |
$339 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | LPG | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | LPG | Personnel Changes | Ancillary Material Cost |