Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Kentucky |
---|---|
Assessment Year | 2012 |
Principal Product | Aluminum Master Alloys, Strontium Metal |
NAICS | 331524 - Aluminum Foundries (except Die-Casting) |
SIC | 3365 - Aluminum Foundries |
Sales | $10,000,000-$50,000,000 |
# of Employees | 51 |
Plant Area (Sq.Ft.) | 92,300 |
Annual Production | 24,000,000 Pounds |
Production Hrs. Annual | 8,400 |
Location (State) | KY |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $229,281 | 8,327,280 | kWh | $0.03 |
Electricity Demand | $253,615 | 24,554 | kW-months/year | $10.33 |
Electricity Fees | $(-63,761) | - | $ | - |
Natural Gas | $222,025 | 49,944 | MMBtu | $4.45 |
TOTAL ENERGY COSTS | $641,160 | |||
RECOMMENDED SAVINGS* | $56,308 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $12,859 Cost: $11,250 |
$7,467 | 271,544 | $5,392 | 522 | - | - |
$7,467 271,544 kWh |
$5,392 522 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $940 Cost: $420 |
$393 | 14,279 | $547 | 53 | - | - |
$393 14,279 kWh |
$547 53 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $7,299 Cost: $7,500 |
$3,973 | 133,551 | $3,326 | 322 | - | - |
$3,973 133,551 kWh |
$3,326 322 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $10,517 Cost: $30,800 |
$4,732 | 172,100 | $5,785 | 560 | - | - |
$4,732 172,100 kWh |
$5,785 560 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $10,493 Cost: $5,984 |
- | - | - | - | $10,493 | 2,358 |
- - kWh |
- - kW-months/year |
$10,493 2,358 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2442 PREHEAT COMBUSTION AIR WITH WASTE HEAT |
Savings: $14,200 Cost: $39,850 |
- | - | - | - | $14,200 | 3,191 |
- - kWh |
- - kW-months/year |
$14,200 3,191 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $56,308 Cost: $95,804 |
$16,565 | 591,474 | $15,050 | 1,457 | $24,693 | 5,549 | $16,565 591,474 kWh |
$15,050 1,457 kW-months/year |
$24,693 5,549 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |