Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Kentucky |
---|---|
Assessment Year | 2016 |
Principal Product | Magazine, Poster, and Book Printing |
NAICS | 323111 - Commercial Printing (except Screen and Books) |
SIC | 2752 - Commercial Printing, Lithographic |
Sales | $50,000,000-$100,000,000 |
# of Employees | 100 |
Plant Area (Sq.Ft.) | 275,000 |
Annual Production | 172,600,000 Units |
Production Hrs. Annual | 6,240 |
Location (State) | KY |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $213,256 | 4,639,680 | kWh | $0.05 |
Electricity Demand | $283,002 | 15,382 | kW-months/year | $18.40 |
Electricity Fees | $5,908 | - | $ | - |
Natural Gas | $99,322 | 16,611 | MMBtu | $5.98 |
TOTAL ENERGY COSTS | $601,488 | |||
RECOMMENDED SAVINGS* | $82,534 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $23,924 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2442 PREHEAT COMBUSTION AIR WITH WASTE HEAT |
Savings: $36,855 Cost: $47,256 |
- | - | - | - | $36,855 | 6,163 | - | - | - | - |
- - kWh |
- - kW-months/year |
$36,855 6,163 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2442 PREHEAT COMBUSTION AIR WITH WASTE HEAT |
Savings: $21,755 Cost: $55,980 |
- | - | - | - | $21,755 | 3,638 | - | - | - | - |
- - kWh |
- - kW-months/year |
$21,755 3,638 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 4.631 INSTALL AN UNINTERUPTABLE POWER SUPPLY |
Savings: $12,000 Cost: $3,000 |
- | - | - | - | - | - | $2,000 | - | $10,000 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$2,000 - $ |
$10,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $840 Cost: - |
$840 | 18,261 | - | - | - | - | - | - | - | - |
$840 18,261 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS |
Savings: $5,216 Cost: $1,200 |
$2,944 | 64,000 | - | - | $2,272 | 380 | - | - | - | - |
$2,944 64,000 kWh |
- - kW-months/year |
$2,272 380 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $4,906 Cost: $2,760 |
$4,906 | 106,655 | - | - | - | - | - | - | - | - |
$4,906 106,655 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $735 Cost: - |
$735 | 15,977 | - | - | - | - | - | - | - | - |
$735 15,977 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $227 Cost: $412 |
$147 | 3,189 | $80 | 4 | - | - | - | - | - | - |
$147 3,189 kWh |
$80 4 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $82,534 Cost: $110,608 |
$9,572 | 208,082 | $80 | 4 | $60,882 | 10,181 | $2,000 | - | $10,000 | - | $9,572 208,082 kWh |
$80 4 kW-months/year |
$60,882 10,181 MMBtu |
$2,000 - $ |
$10,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $23,924 Cost: $7,372 |
$9,572 | 208,082 | $80 | 4 | $2,272 | 380 | $2,000 | - | $10,000 | - | $9,572 208,082 kWh |
$80 4 kW-months/year |
$2,272 380 MMBtu |
$2,000 - $ |
$10,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | One-time Revenue or Avoided Cost |