Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Kentucky |
---|---|
Assessment Year | 2018 |
Principal Product | Ready-to-Eat Frozen Meat and Poultry |
NAICS | 311612 - Meat Processed from Carcasses |
SIC | 2013 - Sausages And Other Prepared Meats |
Sales | $50,000,000-$100,000,000 |
# of Employees | 500 |
Plant Area (Sq.Ft.) | 200,000 |
Annual Production | 84,000,000 Pounds |
Production Hrs. Annual | 7,488 |
Location (State) | KY |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $644,490 | 19,567,200 | kWh | $0.03 |
Electricity Demand | $606,150 | 39,558 | kW-months/year | $15.32 |
Natural Gas | $587,966 | 105,729 | MMBtu | $5.56 |
TOTAL ENERGY COSTS | $2,246,706 | |||
RECOMMENDED SAVINGS* | $120,098 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $35,828 Cost: $14,140 |
- | - | - | - | $35,828 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$35,828 - $ |
- - MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $15,526 Cost: $19,379 |
$9,605 | 291,055 | $5,921 | 387 | - | - | - | - | - | - |
$9,605 291,055 kWh |
$5,921 387 kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $10,079 Cost: $2,780 |
$6,162 | 186,736 | $3,917 | 256 | - | - | - | - | - | - |
$6,162 186,736 kWh |
$3,917 256 kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,905 Cost: $1,700 |
$3,905 | 118,349 | - | - | - | - | - | - | - | - |
$3,905 118,349 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $5,533 Cost: - |
$5,533 | 167,662 | - | - | - | - | - | - | - | - |
$5,533 167,662 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $1,227 Cost: $507 |
$1,227 | 37,185 | - | - | - | - | - | - | - | - |
$1,227 37,185 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4152 USE ONLY CERTIFIED MOTOR REPAIR SHOPS |
Savings: $3,271 Cost: $679 |
$2,108 | 63,888 | $1,163 | 76 | - | - | - | - | - | - |
$2,108 63,888 kWh |
$1,163 76 kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $1,127 Cost: - |
$607 | 18,396 | $520 | 34 | - | - | - | - | - | - |
$607 18,396 kWh |
$520 34 kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $439 Cost: $224 |
- | - | - | - | - | - | $439 | 79 | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$439 79 MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.2163 USE MINIMUM STEAM OPERATING PRESSURE |
Savings: $372 Cost: - |
- | - | - | - | - | - | $372 | 67 | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$372 67 MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 3.4116 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) |
Savings: $42,791 Cost: $10,639 |
- | - | - | - | - | - | - | - | $42,791 | 4,195 |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$42,791 4,195 Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $120,098 Cost: $50,048 |
$29,147 | 883,271 | $11,521 | 753 | $35,828 | - | $811 | 146 | $42,791 | 4,195 | $29,147 883,271 kWh |
$11,521 753 kW-months/year |
$35,828 - $ |
$811 146 MMBtu |
$42,791 4,195 Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal |