Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Louisville |
---|---|
Assessment Year | 1996 |
Principal Product | Exhaust Systems and Subsystems |
NAICS | n/a |
SIC | 3714 - Motor Vehicle Parts And Accessories |
Sales | $5,000,000-$10,000,000 |
# of Employees | 124 |
Plant Area (Sq.Ft.) | 150,000 |
Annual Production | 17,000 Pieces |
Production Hrs. Annual | 4,000 |
Location (State) | IN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $138,642 | 4,603,458 | kWh | $0.03 |
Electricity Demand | $83,842 | 10,021 | kW-months/year | $8.37 |
Electricity Fees | $314 | - | $ | - |
Natural Gas | $26,676 | 5,357 | MMBtu | $4.98 |
TOTAL ENERGY COSTS | $259,474 | |||
RECOMMENDED SAVINGS* | $28,756 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $21,078 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | lb | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,628 Cost: $9,812 |
$2,242 | 74,150 | $1,386 | 188 | - | - |
$2,242 74,150 kWh |
$1,386 188 kW-months/year |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $190 Cost: $20 |
$127 | 4,103 | $63 | 8 | - | - |
$127 4,103 kWh |
$63 8 kW-months/year |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $4,888 Cost: $200 |
$4,888 | 287,808 | - | - | - | - |
$4,888 287,808 kWh |
- - kW-months/year |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.1192 REDUCE SCRAP PRODUCTION |
Savings: $16,000 Cost: $5,000 |
- | - | - | - | $16,000 | 22,500 |
- - kWh |
- - kW-months/year |
$16,000 22,500 lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.5311 RECOVER AND REUSE WASTE MATERIAL |
Savings: $4,050 Cost: - |
- | - | - | - | $4,050 | 1,200 |
- - kWh |
- - kW-months/year |
$4,050 1,200 lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $28,756 Cost: $15,032 |
$7,257 | 366,061 | $1,449 | 196 | $20,050 | 23,700 | $7,257 366,061 kWh |
$1,449 196 kW-months/year |
$20,050 23,700 lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $21,078 Cost: $5,220 |
$5,015 | 291,911 | $63 | 8 | $16,000 | 22,500 | $5,015 291,911 kWh |
$63 8 kW-months/year |
$16,000 22,500 lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | lb | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Electricity Usage | Electricity Demand | Solid Waste (non-haz) |