Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Louisville |
---|---|
Assessment Year | 1996 |
Principal Product | Bulk Materials Handling Equipment |
NAICS | n/a |
SIC | 3535 - Conveyors And Conveying Equipment |
Sales | $5,000,000-$10,000,000 |
# of Employees | 60 |
Plant Area (Sq.Ft.) | 20,000 |
Annual Production | 250 Pieces |
Production Hrs. Annual | 2,040 |
Location (State) | IN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $27,732 | 545,721 | kWh | $0.05 |
Natural Gas | $17,379 | 3,251 | MMBtu | $5.35 |
TOTAL ENERGY COSTS | $48,620 | |||
RECOMMENDED SAVINGS* | $18,014 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $15,979 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Solid Waste (non-haz) | Primary Raw Material | Ancillary Material Cost | Electricity Usage | Natural Gas | Solid Waste (non-haz) | Primary Raw Material | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $40 Cost: $537 |
$40 | 879 | - | - | - | - | - | - | - | - |
$40 879 kWh |
- - MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $1,502 Cost: $500 |
- | - | $1,502 | 281 | - | - | - | - | - | - |
- - kWh |
$1,502 281 MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.5248 SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE |
Savings: $49 Cost: - |
- | - | - | - | $49 | 10,000 | - | - | - | - |
- - kWh |
- - MMBtu |
$49 10,000 lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS |
Savings: $100 Cost: $190 |
- | - | - | - | - | - | - | - | $100 | - |
- - kWh |
- - MMBtu |
- - lb |
- - $ |
$100 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER |
Savings: $393 Cost: - |
- | - | - | - | $393 | 20,800 | - | - | - | - |
- - kWh |
- - MMBtu |
$393 20,800 lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.2123 CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS |
Savings: $15,930 Cost: $7,600 |
- | - | - | - | - | - | $15,600 | - | $330 | - |
- - kWh |
- - MMBtu |
- - lb |
$15,600 - $ |
$330 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $18,014 Cost: $8,827 |
$40 | 879 | $1,502 | 281 | $442 | 30,800 | $15,600 | - | $430 | - | $40 879 kWh |
$1,502 281 MMBtu |
$442 30,800 lb |
$15,600 - $ |
$430 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $15,979 Cost: $7,600 |
- | - | - | - | $49 | 10,000 | $15,600 | - | $330 | - | - - kWh |
- - MMBtu |
$49 10,000 lb |
$15,600 - $ |
$330 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Solid Waste (non-haz) | Primary Raw Material | Ancillary Material Cost | Electricity Usage | Natural Gas | Solid Waste (non-haz) | Primary Raw Material | Ancillary Material Cost |