IAC Assessment: UM0007
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UM0007
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Michigan
Assessment Year 1994
Principal Product Heat Treatment Services
NAICS n/a
SIC 3398 - Metal Heat Treating
Sales $1,000,000-$5,000,000
# of Employees 65
Plant Area (Sq.Ft.) 84,000
Annual Production 91,892,440 Pounds
Production Hrs. Annual 7,200
Location (State) MI
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $131,991 3,075,909 kWh $0.04
Natural Gas $513,636 172,322 MMBtu $2.98
TOTAL ENERGY COSTS $645,627
RECOMMENDED SAVINGS* $30,361 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $13,383
#|Description Savings
Cost
Status Electricity Usage Natural Gas Electricity Usage Natural Gas
$ kWh $ MMBtu
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$5,606
Cost:
$8,840
$5,606 130,422 - - $5,606
130,422
kWh
-
-
MMBtu
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$4,566
Cost:
$19,063
$4,566 106,096 - - $4,566
106,096
kWh
-
-
MMBtu
03: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$1,408
Cost:
$570
$1,408 32,825 - - $1,408
32,825
kWh
-
-
MMBtu
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$1,032
Cost:
$3,000
$1,032 24,033 - - $1,032
24,033
kWh
-
-
MMBtu
05: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR Savings:
$2,179
Cost:
$3,100
$2,179 50,703 - - $2,179
50,703
kWh
-
-
MMBtu
06: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$15,570
Cost:
$6,179
- - $15,570 5,225 -
-
kWh
$15,570
5,225
MMBtu
TOTAL RECOMMENDED Savings:
$30,361
Cost:
$40,752
$14,791 344,079 $15,570 5,225 $14,791
344,079
kWh
$15,570
5,225
MMBtu
TOTAL IMPLEMENTED Savings:
$13,383
Cost:
$34,003
$13,383 311,254 - - $13,383
311,254
kWh
-
-
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Natural Gas Electricity Usage Natural Gas