Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Michigan |
---|---|
Assessment Year | 1995 |
Principal Product | Pressure Vessels |
NAICS | n/a |
SIC | 3443 - Fabricated Plate Work (boiler Shops) |
Sales | $5,000,000-$10,000,000 |
# of Employees | 63 |
Plant Area (Sq.Ft.) | 100,000 |
Annual Production | 7,200 Pounds |
Production Hrs. Annual | 4,160 |
Location (State) | MI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $119,642 | 1,284,291 | kWh | $0.09 |
Natural Gas | $41,669 | 9,530 | MMBtu | $4.37 |
TOTAL ENERGY COSTS | $161,311 | |||
RECOMMENDED SAVINGS* | $7,474 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $4,209 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $1,536 Cost: $621 |
$1,536 | 16,413 | - | - |
$1,536 16,413 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,759 Cost: $7,308 |
$1,759 | 20,223 | - | - |
$1,759 20,223 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $435 Cost: - |
$435 | 4,689 | - | - |
$435 4,689 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,294 Cost: $150 |
$1,294 | 14,068 | - | - |
$1,294 14,068 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7441 REPLACE BROKEN WINDOWS AND/OR WINDOW SASH |
Savings: $2,450 Cost: $2,000 |
- | - | $2,450 | 572 |
- - kWh |
$2,450 572 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $7,474 Cost: $10,079 |
$5,024 | 55,393 | $2,450 | 572 | $5,024 55,393 kWh |
$2,450 572 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $4,209 Cost: $9,308 |
$1,759 | 20,223 | $2,450 | 572 | $1,759 20,223 kWh |
$2,450 572 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |