IAC logo
IAC Assessment: UM0102
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UM0102
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Michigan
Assessment Year 1998
Principal Product Forged Steel Items
NAICS n/a
SIC 3312 - Blast Furnaces And Steel Mills
Sales $5,000,000-$10,000,000
# of Employees 48
Plant Area (Sq.Ft.) 80,000
Annual Production 7,500 Tons
Production Hrs. Annual 2,210
Location (State) OH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $226,284 3,310,082 kWh $0.07
Electricity Demand $97,158 6,300 kW-months/year $15.42
Electricity Fees $11,498 - $ -
Natural Gas $108,940 30,239 MMBtu $3.60
TOTAL ENERGY COSTS $452,160
RECOMMENDED SAVINGS* $48,336 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $763
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Solid Waste (non-haz) Primary Product Electricity Usage Electricity Demand Solid Waste (non-haz) Primary Product
$ kWh $ kW-months/year $ lb $ $
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$334
Cost:
$583
$102 2,638 $232 16 - - - - $102
2,638
kWh
$232
16
kW-months/year
-
-
lb
-
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,544
Cost:
$5,431
$515 13,189 $1,029 71 - - - - $515
13,189
kWh
$1,029
71
kW-months/year
-
-
lb
-
-
$
03: 2.7145 INSTALL SKYLIGHTS Savings:
$562
Cost:
$1,288
$562 9,672 - - - - - - $562
9,672
kWh
-
-
kW-months/year
-
-
lb
-
-
$
04: 3.5311 RECOVER AND REUSE WASTE MATERIAL Savings:
$8,280
Cost:
$250
- - - - $8,280 461,700 - - -
-
kWh
-
-
kW-months/year
$8,280
461,700
lb
-
-
$
05: 4.4310 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY Savings:
$429
Cost:
$160
- - - - - - $429 - -
-
kWh
-
-
kW-months/year
-
-
lb
$429
-
$
06: 4.5130 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS Savings:
$37,187
Cost:
$8,400
- - - - - - $37,187 - -
-
kWh
-
-
kW-months/year
-
-
lb
$37,187
-
$
TOTAL RECOMMENDED Savings:
$48,336
Cost:
$16,112
$1,179 25,499 $1,261 87 $8,280 461,700 $37,616 - $1,179
25,499
kWh
$1,261
87
kW-months/year
$8,280
461,700
lb
$37,616
-
$
TOTAL IMPLEMENTED Savings:
$763
Cost:
$743
$102 2,638 $232 16 - - $429 - $102
2,638
kWh
$232
16
kW-months/year
-
-
lb
$429
-
$
Savings
Cost
$ kWh $ kW-months/year $ lb $ $
Electricity Usage Electricity Demand Solid Waste (non-haz) Primary Product Electricity Usage Electricity Demand Solid Waste (non-haz) Primary Product