Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Michigan |
---|---|
Assessment Year | 2003 |
Principal Product | Extruded Rubber Hoses |
NAICS | 326291 - Rubber Product Manufacturing for Mechanical Use |
SIC | 3061 - Mechanical Rubber Goods |
Sales | $50,000,000-$100,000,000 |
# of Employees | 465 |
Plant Area (Sq.Ft.) | 236,000 |
Annual Production | 40,000,000 Pounds |
Production Hrs. Annual | 6,000 |
Location (State) | MI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $394,674 | 12,603,243 | kWh | $0.03 |
Electricity Demand | $286,402 | 30,152 | kW-months/year | $9.50 |
Electricity Fees | $99,317 | - | $ | - |
Natural Gas | $919,294 | 179,762 | MMBtu | $5.11 |
TOTAL ENERGY COSTS | $2,047,687 | |||
RECOMMENDED SAVINGS* | $274,781 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $135,839 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $7,438 Cost: $21,682 |
$5,125 | 170,654 | $2,313 | 295 | - | - | - | - | - | - |
$5,125 170,654 kWh |
$2,313 295 kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS |
Savings: $2,265 Cost: $700 |
- | - | - | - | - | - | $2,265 | 498 | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$2,265 498 MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $21,643 Cost: $15,930 |
- | - | - | - | $21,643 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$21,643 - $ |
- - MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.4111 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION |
Savings: $51,840 Cost: $5,520 |
- | - | - | - | - | - | - | - | $51,840 | 8,640,000 |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$51,840 8,640,000 Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS |
Savings: $26,100 Cost: $7,230 |
- | - | - | - | - | - | $26,100 | 4,085 | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$26,100 4,085 MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.3131 USE EVAPORATION TO CONCENTRATE MATERIAL |
Savings: $57,600 Cost: $19,600 |
- | - | - | - | - | - | $(-14,600) | (-2,887) | $72,200 | 3,192,600 |
- - kWh |
- - kW-months/year |
- - $ |
$(-14,600) (-2,887) MMBtu |
$72,200 3,192,600 Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $2,606 Cost: $934 |
- | - | - | - | - | - | $2,606 | 516 | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$2,606 516 MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2111 INSTALL STEAM TRAP |
Savings: $1,031 Cost: $4,360 |
- | - | - | - | - | - | $232 | 46 | $799 | 35,347 |
- - kWh |
- - kW-months/year |
- - $ |
$232 46 MMBtu |
$799 35,347 Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4235 REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES |
Savings: $2,650 Cost: $120 |
$1,387 | 44,300 | $1,263 | 133 | - | - | - | - | - | - |
$1,387 44,300 kWh |
$1,263 133 kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $53,338 Cost: $12,600 |
$33,200 | 1,103,651 | $20,138 | 2,207 | - | - | - | - | - | - |
$33,200 1,103,651 kWh |
$20,138 2,207 kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.3191 USE DEMAND CONTROLLER OR LOAD SHEDDER |
Savings: $17,270 Cost: $10,000 |
- | - | $17,270 | 2,309 | - | - | - | - | - | - |
- - kWh |
$17,270 2,309 kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $31,000 Cost: $2,500 |
- | - | - | - | - | - | $31,000 | 6,290 | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$31,000 6,290 MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $274,781 Cost: $101,176 |
$39,712 | 1,318,605 | $40,984 | 4,944 | $21,643 | - | $47,603 | 8,548 | $124,839 | 11,867,947 | $39,712 1,318,605 kWh |
$40,984 4,944 kW-months/year |
$21,643 - $ |
$47,603 8,548 MMBtu |
$124,839 11,867,947 Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $135,839 Cost: $32,234 |
$1,387 | 44,300 | $1,263 | 133 | $21,643 | - | $59,706 | 10,891 | $51,840 | 8,640,000 | $1,387 44,300 kWh |
$1,263 133 kW-months/year |
$21,643 - $ |
$59,706 10,891 MMBtu |
$51,840 8,640,000 Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal |