Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Michigan |
---|---|
Assessment Year | 2004 |
Principal Product | Machine Glazed Paper |
NAICS | 322121 - Paper (except Newsprint) Mills |
SIC | 2621 - Paper Mills |
Sales | $100,000,000-$500,000,000 |
# of Employees | 290 |
Plant Area (Sq.Ft.) | 318,000 |
Annual Production | 32,000 Tons |
Production Hrs. Annual | 8,736 |
Location (State) | MI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $612,681 | 26,686,278 | kWh | $0.02 |
Electricity Demand | $235,834 | 52,834 | kW-months/year | $4.46 |
Electricity Fees | $8,547 | - | $ | - |
Natural Gas | $122,467 | 24,319 | MMBtu | $5.04 |
Coal | $1,177,963 | 376,000 | MMBtu | $3.13 |
TOTAL ENERGY COSTS | $2,157,493 | |||
RECOMMENDED SAVINGS* | $782,781 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Coal | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Coal | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.1331 BURN A LESS EXPENSIVE GRADE OF FUEL |
Savings: $542,255 Cost: $2,000,000 |
- | - | - | - | - | - | - | - | $542,255 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
$542,255 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2449 RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER |
Savings: $145,057 Cost: $125,000 |
- | - | - | - | - | - | $145,057 | 46,344 | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$145,057 46,344 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS |
Savings: $46,000 Cost: $46,000 |
- | - | - | - | - | - | $46,000 | 15,371 | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$46,000 15,371 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2449 RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER |
Savings: $24,731 Cost: $30,000 |
- | - | - | - | $24,731 | 4,907 | - | - | - | - |
- - kWh |
- - kW-months/year |
$24,731 4,907 MMBtu |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $11,485 Cost: $27,143 |
$9,066 | 394,868 | $2,419 | 542 | - | - | - | - | - | - |
$9,066 394,868 kWh |
$2,419 542 kW-months/year |
- - MMBtu |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $9,777 Cost: $975 |
$7,731 | 336,145 | $2,046 | 462 | - | - | - | - | - | - |
$7,731 336,145 kWh |
$2,046 462 kW-months/year |
- - MMBtu |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7491 INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS |
Savings: $2,064 Cost: $1,921 |
- | - | - | - | $2,064 | 328 | - | - | - | - |
- - kWh |
- - kW-months/year |
$2,064 328 MMBtu |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,412 Cost: $828 |
$1,412 | 61,503 | - | - | - | - | - | - | - | - |
$1,412 61,503 kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $782,781 Cost: $2,231,867 |
$18,209 | 792,516 | $4,465 | 1,004 | $26,795 | 5,235 | $191,057 | 61,715 | $542,255 | - | $18,209 792,516 kWh |
$4,465 1,004 kW-months/year |
$26,795 5,235 MMBtu |
$191,057 61,715 MMBtu |
$542,255 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Coal | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Coal | Administrative Changes |