Select a Center

Arizona State University
Boise State University
Case Western Reserve University
Clemson University
Colorado State University
Georgia Institute of Technology
Indiana University-Purdue University
Lehigh University
Louisiana State University
North Carolina State
Oklahoma State University
Oregon State University
San Diego State University
San Francisco State University
Syracuse University
Tennessee Technological University
Texas A&M, College Station
University of Alabama
University of Dayton
University of Delaware
University of Florida
University of Illinois, Chicago
University of Kentucky
University of Massachusetts
University of Miami
University of Missouri-Columbia
University of Nebraska–Lincoln
University of Texas Rio Grande Valley
University of Utah
University of Wisconsin, Milwaukee
West Virginia University
IAC logo
IAC Assessment: UM0481
Sponsored by:
EERE AMO
IAC logo
IAC Assessment: UM0481
IAC Center University of Michigan
Assessment Year 2017
Principal Product Customized, un-cured, bulk silicone elastomer
NAICS 325199 - All Other Basic Organic Chemical Manufacturing
SIC 3069 - Fabricated Rubber Products, Nec
Sales $50,000,000
# of Employees 80
Plant Area (Sq.Ft.) 94,600
Annual Production 25,353,160 Pounds
Production Hrs. Annual 8,544
Location (State) IN
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $387,757 3,953,370 kWh $0.10
Natural Gas $25,360 4,053 MMBtu $6.26
TOTAL ENERGY COSTS $413,117
RECOMMENDED SAVINGS* $98,929 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Natural Gas Primary Raw Material Electricity Usage Natural Gas Primary Raw Material
$ kWh $ MMBtu $ $
01: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$7,978
Cost:
$3,000
$11,239 114,683 $(-3,261) (-522) - - $11,239
114,683
kWh
$(-3,261)
(-522)
MMBtu
-
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$21,854
Cost:
$34,336
$21,854 222,998 - - - - $21,854
222,998
kWh
-
-
MMBtu
-
-
$
03: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$18,599
Cost:
$6,600
$18,599 189,784 - - - - $18,599
189,784
kWh
-
-
MMBtu
-
-
$
04: 2.1336 INSTALL EQUIPMENT TO UTILIZE WASTE FUEL Savings:
$50,498
Cost:
$100,000
- - - - $50,498 - -
-
kWh
-
-
MMBtu
$50,498
-
$
TOTAL RECOMMENDED Savings:
$98,929
Cost:
$143,936
$51,692 527,465 $(-3,261) (-522) $50,498 - $51,692
527,465
kWh
$(-3,261)
(-522)
MMBtu
$50,498
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - -
-
kWh
-
-
MMBtu
-
-
$
Savings
Cost
$ kWh $ MMBtu $ $
Electricity Usage Natural Gas Primary Raw Material Electricity Usage Natural Gas Primary Raw Material