IAC Assessment: UU0124
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UU0124
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Utah
Assessment Year 2017
Principal Product NA
NAICS 712130 - Zoos and Botanical Gardens
SIC 7999 - Amusement And Recreation, Nec
Sales $10,000,000-$50,000,000
# of Employees 100
Plant Area (Sq.Ft.) 1,873,000
Annual Production 1,000,000 Units
Production Hrs. Annual 3,150
Location (State) UT
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $141,778 3,341,177 kWh $0.04
Electricity Demand $97,338 9,007 kW-months/year $10.81
Electricity Fees $137,517 - $ -
Natural Gas $119,929 40,406 MMBtu $2.97
TOTAL ENERGY COSTS $496,562
RECOMMENDED SAVINGS* $30,703 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $20,848
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Natural Gas Electricity Usage Electricity Demand Electricity Fees Natural Gas
$ kWh $ kW-months/year $ $ $ MMBtu
01: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$12,503
Cost:
-
- - $9,796 670 $2,707 - - - -
-
kWh
$9,796
670
kW-months/year
$2,707
-
$
-
-
MMBtu
02: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$5,444
Cost:
$5,000
- - - - $5,444 - - - -
-
kWh
-
-
kW-months/year
$5,444
-
$
-
-
MMBtu
03: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$4,630
Cost:
$3,140
$1,920 45,386 $2,537 206 $832 - $(-660) (-155) $1,920
45,386
kWh
$2,537
206
kW-months/year
$832
-
$
$(-660)
(-155)
MMBtu
04: 2.7423 REDUCE HEAT GAIN BY WINDOW TINTING Savings:
$3,392
Cost:
$10,800
$2,329 55,066 $801 65 $263 - - - $2,329
55,066
kWh
$801
65
kW-months/year
$263
-
$
-
-
MMBtu
05: 2.2622 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL Savings:
$1,833
Cost:
$4,266
$1,335 31,554 $375 30 $123 - - - $1,335
31,554
kWh
$375
30
kW-months/year
$123
-
$
-
-
MMBtu
06: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$980
Cost:
-
- - - - - - $980 230 -
-
kWh
-
-
kW-months/year
-
-
$
$980
230
MMBtu
07: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS Savings:
$854
Cost:
$1,702
$178 4,217 $200 16 $65 - $410 96 $178
4,217
kWh
$200
16
kW-months/year
$65
-
$
$410
96
MMBtu
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$681
Cost:
$1,463
$263 6,214 $315 26 $103 - - - $263
6,214
kWh
$315
26
kW-months/year
$103
-
$
-
-
MMBtu
09: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS Savings:
$386
Cost:
-
$333 7,868 - - - - $53 12 $333
7,868
kWh
-
-
kW-months/year
-
-
$
$53
12
MMBtu
TOTAL RECOMMENDED Savings:
$30,703
Cost:
$26,371
$6,358 150,305 $14,023 1,013 $9,538 - $784 184 $6,358
150,305
kWh
$14,023
1,013
kW-months/year
$9,538
-
$
$784
184
MMBtu
TOTAL IMPLEMENTED Savings:
$20,848
Cost:
$8,165
$774 18,299 $10,310 712 $8,320 - $1,444 339 $774
18,299
kWh
$10,310
712
kW-months/year
$8,320
-
$
$1,444
339
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ $ $ MMBtu
Electricity Usage Electricity Demand Electricity Fees Natural Gas Electricity Usage Electricity Demand Electricity Fees Natural Gas