Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Utah
Assessment Year 2018
Principal Product Machinery
NAICS 333249 - Other Industrial Machinery Manufacturing
SIC 3569 - General Industrial Machinery, Nec
Sales $10,000,000-$50,000,000
# of Employees 100
Plant Area (Sq.Ft.) 150,000
Annual Production 150,000 Pieces
Production Hrs. Annual 4,680
Location (State) UT
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $78,634 1,650,160 kWh $0.05
Electricity Demand $84,441 6,854 kW-months/year $12.32
Electricity Fees $22,397 - $ -
Natural Gas $10,594 1,300 MMBtu $8.15
TOTAL ENERGY COSTS $196,066
RECOMMENDED SAVINGS* $27,479 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $27,479
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Ancillary Material Cost One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Electricity Fees Ancillary Material Cost One-time Revenue or Avoided Cost
$ kWh $ kW-months/year $ $ $ $ $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$14,221
Cost:
$18,137
$8,148 169,753 $5,840 474 - - $233 - - - $8,148
169,753
kWh
$5,840
474
kW-months/year
-
-
$
$233
-
$
-
-
$
02: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$9,044
Cost:
$2,760
- - $9,908 600 $(-864) - - - - - -
-
kWh
$9,908
600
kW-months/year
$(-864)
-
$
-
-
$
-
-
$
03: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$1,911
Cost:
-
$1,911 39,810 - - - - - - - - $1,911
39,810
kWh
-
-
kW-months/year
-
-
$
-
-
$
-
-
$
04: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$1,089
Cost:
$1,500
$1,089 22,690 - - - - - - - - $1,089
22,690
kWh
-
-
kW-months/year
-
-
$
-
-
$
-
-
$
05: 2.7241 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT Savings:
$615
Cost:
-
$615 12,816 - - - - - - - - $615
12,816
kWh
-
-
kW-months/year
-
-
$
-
-
$
-
-
$
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$599
Cost:
$150
$32 664 - - - - - - $567 - $32
664
kWh
-
-
kW-months/year
-
-
$
-
-
$
$567
-
$
TOTAL RECOMMENDED Savings:
$27,479
Cost:
$22,547
$11,795 245,733 $15,748 1,074 $(-864) - $233 - $567 - $11,795
245,733
kWh
$15,748
1,074
kW-months/year
$(-864)
-
$
$233
-
$
$567
-
$
TOTAL IMPLEMENTED Savings:
$27,479
Cost:
$22,547
$11,795 245,733 $15,748 1,074 $(-864) - $233 - $567 - $11,795
245,733
kWh
$15,748
1,074
kW-months/year
$(-864)
-
$
$233
-
$
$567
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $ $ $
Electricity Usage Electricity Demand Electricity Fees Ancillary Material Cost One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Electricity Fees Ancillary Material Cost One-time Revenue or Avoided Cost