Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Utah |
---|---|
Assessment Year | 2021 |
Principal Product | Treated Wastewater |
NAICS | 221310 - Water Supply and Irrigation Systems |
SIC | 4952 - Sewerage Systems |
Sales | $10,000,000-$50,000,000 |
# of Employees | 33 |
Plant Area (Sq.Ft.) | 105,000 |
Annual Production | 11,680,000 Thousand Gallons |
Production Hrs. Annual | 8,760 |
Location (State) | UT |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $376,194 | 11,510,400 | kWh | $0.03 |
Electricity Demand | $269,768 | 19,738 | kW-months/year | $13.67 |
Electricity Fees | $17,258 | - | $ | - |
Natural Gas | $146,506 | 24,116 | MMBtu | $6.08 |
TOTAL ENERGY COSTS | $809,726 | |||
RECOMMENDED SAVINGS* | $446,395 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $190,992 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.6125 SELL COMBUSTIBLE WASTE |
Savings: $149,294 Cost: $144,000 |
- | - | - | - | - | - | $149,294 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$149,294 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1336 INSTALL EQUIPMENT TO UTILIZE WASTE FUEL |
Savings: $118,667 Cost: $7,000 |
- | - | - | - | $118,667 | 21,704 | - | - |
- - kWh |
- - kW-months/year |
$118,667 21,704 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $100,049 Cost: $157,500 |
$100,049 | 3,031,779 | - | - | - | - | - | - |
$100,049 3,031,779 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $35,893 Cost: $14,200 |
- | - | - | - | - | - | $35,893 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$35,893 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.3128 UTILIZE OTHER METHODS TO REMOVE CONTAMINANTS |
Savings: $19,111 Cost: $20,527 |
$19,111 | 579,121 | - | - | - | - | - | - |
$19,111 579,121 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7226 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE |
Savings: $15,681 Cost: $1,607 |
$5,348 | 162,066 | - | - | $10,333 | 1,701 | - | - |
$5,348 162,066 kWh |
- - kW-months/year |
$10,333 1,701 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $6,906 Cost: $22,506 |
$2,098 | 63,585 | $4,807 | 352 | - | - | - | - |
$2,098 63,585 kWh |
$4,807 352 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS |
Savings: $794 Cost: $1,175 |
$(-57) | (-1,740) | - | - | $851 | 140 | - | - |
$(-57) (-1,740) kWh |
- - kW-months/year |
$851 140 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $446,395 Cost: $368,515 |
$126,549 | 3,834,811 | $4,807 | 352 | $129,851 | 23,545 | $185,187 | - | $126,549 3,834,811 kWh |
$4,807 352 kW-months/year |
$129,851 23,545 MMBtu |
$185,187 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $190,992 Cost: $188,640 |
$26,557 | 804,772 | $4,807 | 352 | $10,333 | 1,701 | $149,294 | - | $26,557 804,772 kWh |
$4,807 352 kW-months/year |
$10,333 1,701 MMBtu |
$149,294 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes |