IAC Assessment: WI0075
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: WI0075
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Wisconsin, Milwaukee
Assessment Year 1989
Principal Product RESINS
NAICS n/a
SIC 2899 - Chemical Preparations, Nec
Sales $10,000,000-$50,000,000
# of Employees 50
Plant Area (Sq.Ft.) 0
Annual Production 10,000,000 Pounds
Production Hrs. Annual 2,210
Location (State) WI
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $26,053 356,975 kWh $0.07
Natural Gas $19,512 4,039 MMBtu $4.83
Fuel Oil #2 $44,773 8,960 MMBtu $5.00
TOTAL ENERGY COSTS $90,338
RECOMMENDED SAVINGS* $11,229 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $5,198
#|Description Savings
Cost
Status Electricity Usage Natural Gas Fuel Oil #2 Electricity Usage Natural Gas Fuel Oil #2
$ kWh $ MMBtu $ MMBtu
01: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS Savings:
$3,157
Cost:
$3,100
- - - - $3,157 631 -
-
kWh
-
-
MMBtu
$3,157
631
MMBtu
02: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$2,866
Cost:
$500
- - - - $2,866 573 -
-
kWh
-
-
MMBtu
$2,866
573
MMBtu
03: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$2,210
Cost:
$5,000
- - - - $2,210 442 -
-
kWh
-
-
MMBtu
$2,210
442
MMBtu
04: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$898
Cost:
$250
- - $898 186 - - -
-
kWh
$898
186
MMBtu
-
-
MMBtu
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$227
Cost:
$104
$227 3,224 - - - - $227
3,224
kWh
-
-
MMBtu
-
-
MMBtu
06: 2.7494 INSTALL STORM WINDOWS AND DOORS Savings:
$671
Cost:
$1,144
- - - - $671 134 -
-
kWh
-
-
MMBtu
$671
134
MMBtu
07: 2.4312 IMPROVE LUBRICATION PRACTICES Savings:
$590
Cost:
-
$590 8,206 - - - - $590
8,206
kWh
-
-
MMBtu
-
-
MMBtu
08: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$291
Cost:
$700
$406 5,569 $(-115) (-24) - - $406
5,569
kWh
$(-115)
(-24)
MMBtu
-
-
MMBtu
09: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$245
Cost:
$165
- - - - $245 49 -
-
kWh
-
-
MMBtu
$245
49
MMBtu
10: 2.6232 INSTALL SET-BACK TIMERS Savings:
$74
Cost:
$200
$74 1,172 - - - - $74
1,172
kWh
-
-
MMBtu
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$11,229
Cost:
$11,163
$1,297 18,171 $783 162 $9,149 1,829 $1,297
18,171
kWh
$783
162
MMBtu
$9,149
1,829
MMBtu
TOTAL IMPLEMENTED Savings:
$5,198
Cost:
$4,763
$227 3,224 $898 186 $4,073 814 $227
3,224
kWh
$898
186
MMBtu
$4,073
814
MMBtu
Savings
Cost
$ kWh $ MMBtu $ MMBtu
Electricity Usage Natural Gas Fuel Oil #2 Electricity Usage Natural Gas Fuel Oil #2