Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Wisconsin, Milwaukee |
---|---|
Assessment Year | 1995 |
Principal Product | Molded Rubber |
NAICS | n/a |
SIC | 3069 - Fabricated Rubber Products, Nec |
Sales | $5,000,000-$10,000,000 |
# of Employees | 73 |
Plant Area (Sq.Ft.) | 102,000 |
Annual Production | 500,000 Pounds |
Production Hrs. Annual | 6,000 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $155,150 | 1,832,356 | kWh | $0.08 |
Natural Gas | $55,721 | 15,214 | MMBtu | $3.66 |
TOTAL ENERGY COSTS | $256,571 | |||
RECOMMENDED SAVINGS* | $24,526 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $4,083 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Water Disposal | Solid Waste (non-haz) | Electricity Usage | Natural Gas | Water Disposal | Solid Waste (non-haz) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | Tgal | $ | lb | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $4,083 Cost: $4,041 |
$4,083 | 48,359 | - | - | - | - | - | - |
$4,083 48,359 kWh |
- - MMBtu |
- - Tgal |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7314 REDUCE VENTILATION AIR |
Savings: $603 Cost: $1,000 |
$70 | 879 | $533 | 146 | - | - | - | - |
$70 879 kWh |
$533 146 MMBtu |
- - Tgal |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $1,090 Cost: $100 |
$1,090 | 12,896 | - | - | - | - | - | - |
$1,090 12,896 kWh |
- - MMBtu |
- - Tgal |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $578 Cost: - |
$578 | 6,741 | - | - | - | - | - | - |
$578 6,741 kWh |
- - MMBtu |
- - Tgal |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $293 Cost: $640 |
$293 | 3,517 | - | - | - | - | - | - |
$293 3,517 kWh |
- - MMBtu |
- - Tgal |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2612 USE COOLING TOWER WATER INSTEAD OF REFRIGERATION |
Savings: $16,579 Cost: $22,000 |
- | - | - | - | $16,579 | 10,000,000 | - | - |
- - kWh |
- - MMBtu |
$16,579 10,000,000 Tgal |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS |
Savings: $1,300 Cost: - |
- | - | - | - | - | - | $1,300 | - |
- - kWh |
- - MMBtu |
- - Tgal |
$1,300 - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $24,526 Cost: $27,781 |
$6,114 | 72,392 | $533 | 146 | $16,579 | 10,000,000 | $1,300 | - | $6,114 72,392 kWh |
$533 146 MMBtu |
$16,579 10,000,000 Tgal |
$1,300 - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $4,083 Cost: $4,041 |
$4,083 | 48,359 | - | - | - | - | - | - | $4,083 48,359 kWh |
- - MMBtu |
- - Tgal |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | Tgal | $ | lb | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Water Disposal | Solid Waste (non-haz) | Electricity Usage | Natural Gas | Water Disposal | Solid Waste (non-haz) |