Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Wisconsin, Milwaukee |
---|---|
Assessment Year | 1996 |
Principal Product | Mining Locomotives, Industrial Blow Molding Machines |
NAICS | n/a |
SIC | 3532 - Mining Machinery |
Sales | $10,000,000-$50,000,000 |
# of Employees | 87 |
Plant Area (Sq.Ft.) | 63,000 |
Annual Production | 62 Pieces |
Production Hrs. Annual | 2,294 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $49,701 | 473,916 | kWh | $0.10 |
Electricity Demand | $29,431 | 2,406 | kW-months/year | $12.23 |
Electricity Fees | $(-364) | - | $ | - |
Natural Gas | $9,413 | 2,754 | MMBtu | $3.42 |
TOTAL ENERGY COSTS | $88,181 | |||
RECOMMENDED SAVINGS* | $16,904 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $10,442 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (haz) | Primary Raw Material | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (haz) | Primary Raw Material | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS |
Savings: $8,700 Cost: - |
- | - | - | - | - | - | - | - | $8,700 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
$8,700 - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $2,497 Cost: $700 |
$819 | 18,757 | $1,898 | 148 | $(-220) | (-64) | - | - | - | - | - | - |
$819 18,757 kWh |
$1,898 148 kW-months/year |
$(-220) (-64) MMBtu |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.2123 CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS |
Savings: $1,508 Cost: $500 |
- | - | - | - | - | - | - | - | - | - | $1,508 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
$1,508 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7251 REDUCE AIR CONDITIONING LOAD BY EVAPORATING WATER FROM ROOF |
Savings: $1,202 Cost: $3,900 |
$625 | 14,361 | $577 | 45 | - | - | - | - | - | - | - | - |
$625 14,361 kWh |
$577 45 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $1,130 Cost: $1,900 |
- | - | - | - | $1,130 | 339 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,130 339 MMBtu |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $125 Cost: $250 |
- | - | - | - | $125 | 37 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$125 37 MMBtu |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.8124 INSTALL FLOATING COVERS ON TANKS OF VOLATILE MATERIALS TO REDUCE EVAPORATION |
Savings: $873 Cost: - |
- | - | - | - | - | - | $873 | 195 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$873 195 gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $280 Cost: $600 |
$280 | 2,052 | - | - | - | - | - | - | - | - | - | - |
$280 2,052 kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $172 Cost: $85 |
$80 | 1,758 | $92 | 7 | - | - | - | - | - | - | - | - |
$80 1,758 kWh |
$92 7 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $124 Cost: $60 |
$62 | 1,465 | $62 | 5 | - | - | - | - | - | - | - | - |
$62 1,465 kWh |
$62 5 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $293 Cost: $640 |
$108 | 2,345 | $185 | 14 | - | - | - | - | - | - | - | - |
$108 2,345 kWh |
$185 14 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $16,904 Cost: $8,635 |
$1,974 | 40,738 | $2,814 | 219 | $1,035 | 312 | $873 | 195 | $8,700 | - | $1,508 | - | $1,974 40,738 kWh |
$2,814 219 kW-months/year |
$1,035 312 MMBtu |
$873 195 gal |
$8,700 - lb |
$1,508 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $10,442 Cost: $1,385 |
$530 | 7,620 | $339 | 26 | - | - | $873 | 195 | $8,700 | - | - | - | $530 7,620 kWh |
$339 26 kW-months/year |
- - MMBtu |
$873 195 gal |
$8,700 - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (haz) | Primary Raw Material | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (haz) | Primary Raw Material |