Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Wisconsin, Milwaukee |
---|---|
Assessment Year | 1997 |
Principal Product | Home Furnishings |
NAICS | n/a |
SIC | 3645 - Residential Lighting Fixtures |
Sales | $10,000,000-$50,000,000 |
# of Employees | 530 |
Plant Area (Sq.Ft.) | 454,900 |
Annual Production | 375,000 Pieces |
Production Hrs. Annual | 3,000 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $114,287 | 2,758,499 | kWh | $0.04 |
Electricity Demand | $168,128 | 12,053 | kW-months/year | $13.95 |
Electricity Fees | $17,026 | - | $ | - |
Natural Gas | $187,744 | 51,283 | MMBtu | $3.66 |
TOTAL ENERGY COSTS | $561,027 | |||
RECOMMENDED SAVINGS* | $173,533 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $142,548 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (haz) | Personnel Changes | Primary Raw Material | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (haz) | Personnel Changes | Primary Raw Material | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.2123 CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS |
Savings: $119,620 Cost: $15,000 |
- | - | - | - | - | - | - | - | - | - | $119,620 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
$119,620 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7314 REDUCE VENTILATION AIR |
Savings: $10,493 Cost: $15,000 |
$1,504 | 34,584 | - | - | $8,989 | 2,456 | - | - | - | - | - | - |
$1,504 34,584 kWh |
- - kW-months/year |
$8,989 2,456 MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS |
Savings: $7,560 Cost: $5,000 |
- | - | - | - | - | - | $7,560 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$7,560 - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $10,200 Cost: $15,000 |
$7,904 | 181,419 | $9,856 | 671 | $(-7,560) | (-2,065) | - | - | - | - | - | - |
$7,904 181,419 kWh |
$9,856 671 kW-months/year |
$(-7,560) (-2,065) MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $7,755 Cost: $330 |
$3,857 | 88,511 | $3,898 | 265 | - | - | - | - | - | - | - | - |
$3,857 88,511 kWh |
$3,898 265 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $1,526 Cost: $1,380 |
$522 | 12,016 | $1,004 | 68 | - | - | - | - | - | - | - | - |
$522 12,016 kWh |
$1,004 68 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $7,982 Cost: - |
- | - | $8,332 | 568 | - | - | - | - | $(-350) | - | - | - |
- - kWh |
$8,332 568 kW-months/year |
- - MMBtu |
- - lb |
$(-350) - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $5,333 Cost: $500 |
- | - | - | - | $5,333 | 1,457 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$5,333 1,457 MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $2,280 Cost: $1,120 |
- | - | - | - | $2,280 | 623 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$2,280 623 MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 4.321 OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES |
Savings: $784 Cost: - |
- | - | - | - | - | - | - | - | - | - | $784 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
$784 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $173,533 Cost: $53,330 |
$13,787 | 316,530 | $23,090 | 1,572 | $9,042 | 2,471 | $7,560 | - | $(-350) | - | $120,404 | - | $13,787 316,530 kWh |
$23,090 1,572 kW-months/year |
$9,042 2,471 MMBtu |
$7,560 - lb |
$(-350) - $ |
$120,404 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $142,548 Cost: $21,950 |
$3,857 | 88,511 | $3,898 | 265 | $7,613 | 2,080 | $7,560 | - | - | - | $119,620 | - | $3,857 88,511 kWh |
$3,898 265 kW-months/year |
$7,613 2,080 MMBtu |
$7,560 - lb |
- - $ |
$119,620 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (haz) | Personnel Changes | Primary Raw Material | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (haz) | Personnel Changes | Primary Raw Material |