IAC Assessment: WI0300
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: WI0300
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Wisconsin, Milwaukee
Assessment Year 1997
Principal Product Molded and non-molded chemical products
NAICS n/a
SIC 2899 - Chemical Preparations, Nec
Sales $10,000,000-$50,000,000
# of Employees 122
Plant Area (Sq.Ft.) 85,000
Annual Production 67,000,000 Pieces
Production Hrs. Annual 3,550
Location (State) IL
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $57,527 1,321,805 kWh $0.04
Electricity Demand $52,736 4,257 kW-months/year $12.39
Electricity Fees $2,007 - $ -
Natural Gas $75,846 18,319 MMBtu $4.14
TOTAL ENERGY COSTS $217,628
RECOMMENDED SAVINGS* $90,093 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $66,700
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Water Disposal Other Liquid (haz) Solid Waste (non-haz) Personnel Changes Primary Raw Material Electricity Usage Electricity Demand Natural Gas Water Disposal Other Liquid (haz) Solid Waste (non-haz) Personnel Changes Primary Raw Material
$ kWh $ kW-months/year $ MMBtu $ Tgal $ gal $ lb $ $ $ $
01: 4.445 INSTALL EQUIPMENT TO MOVE PRODUCT Savings:
$61,113
Cost:
$30,000
$(-356) (-7,327) $(-406) (-30) - - - - - - - - $61,875 - - - $(-356)
(-7,327)
kWh
$(-406)
(-30)
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
gal
-
-
lb
$61,875
-
$
-
-
$
02: 3.4114 REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER Savings:
$11,999
Cost:
$17,000
$(-953) (-19,930) $(-689) (-50) $8,557 2,067 $5,084 1,533,600 - - - - - - - - $(-953)
(-19,930)
kWh
$(-689)
(-50)
kW-months/year
$8,557
2,067
MMBtu
$5,084
1,533,600
Tgal
-
-
gal
-
-
lb
-
-
$
-
-
$
03: 3.8142 DISTILL CONTAMINATED SOLVENTS FOR REUSE Savings:
$5,148
Cost:
$17,000
- - - - - - - - $4,980 660 $(-181) (-271) $(-938) - $1,287 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
$4,980
660
gal
$(-181)
(-271)
lb
$(-938)
-
$
$1,287
-
$
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$2,810
Cost:
$90
$1,632 33,998 $1,178 86 - - - - - - - - - - - - $1,632
33,998
kWh
$1,178
86
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
gal
-
-
lb
-
-
$
-
-
$
05: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$606
Cost:
$640
$352 7,327 $254 19 - - - - - - - - - - - - $352
7,327
kWh
$254
19
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
gal
-
-
lb
-
-
$
-
-
$
06: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$2,192
Cost:
-
- - - - $2,192 529 - - - - - - - - - - -
-
kWh
-
-
kW-months/year
$2,192
529
MMBtu
-
-
Tgal
-
-
gal
-
-
lb
-
-
$
-
-
$
07: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$1,932
Cost:
$400
- - - - $1,932 467 - - - - - - - - - - -
-
kWh
-
-
kW-months/year
$1,932
467
MMBtu
-
-
Tgal
-
-
gal
-
-
lb
-
-
$
-
-
$
08: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$1,355
Cost:
$500
- - - - $1,355 327 - - - - - - - - - - -
-
kWh
-
-
kW-months/year
$1,355
327
MMBtu
-
-
Tgal
-
-
gal
-
-
lb
-
-
$
-
-
$
09: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS Savings:
$1,241
Cost:
$2,739
- - - - $1,241 300 - - - - - - - - - - -
-
kWh
-
-
kW-months/year
$1,241
300
MMBtu
-
-
Tgal
-
-
gal
-
-
lb
-
-
$
-
-
$
10: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$1,112
Cost:
$5,000
$1,112 23,154 - - - - - - - - - - - - - - $1,112
23,154
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
gal
-
-
lb
-
-
$
-
-
$
11: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS Savings:
$585
Cost:
-
- - $585 38 - - - - - - - - - - - - -
-
kWh
$585
38
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
gal
-
-
lb
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$90,093
Cost:
$73,369
$1,787 37,222 $922 63 $15,277 3,690 $5,084 1,533,600 $4,980 660 $(-181) (-271) $60,937 - $1,287 - $1,787
37,222
kWh
$922
63
kW-months/year
$15,277
3,690
MMBtu
$5,084
1,533,600
Tgal
$4,980
660
gal
$(-181)
(-271)
lb
$60,937
-
$
$1,287
-
$
TOTAL IMPLEMENTED Savings:
$66,700
Cost:
$30,090
$1,276 26,671 $1,357 94 $2,192 529 - - - - - - $61,875 - - - $1,276
26,671
kWh
$1,357
94
kW-months/year
$2,192
529
MMBtu
-
-
Tgal
-
-
gal
-
-
lb
$61,875
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ Tgal $ gal $ lb $ $ $ $
Electricity Usage Electricity Demand Natural Gas Water Disposal Other Liquid (haz) Solid Waste (non-haz) Personnel Changes Primary Raw Material Electricity Usage Electricity Demand Natural Gas Water Disposal Other Liquid (haz) Solid Waste (non-haz) Personnel Changes Primary Raw Material