Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Wisconsin, Milwaukee |
---|---|
Assessment Year | 1998 |
Principal Product | Steel Rolls |
NAICS | n/a |
SIC | 3547 - Rolling Mill Machinery |
Sales | $1,000,000-$5,000,000 |
# of Employees | 32 |
Plant Area (Sq.Ft.) | 30,000 |
Annual Production | 600 Pieces |
Production Hrs. Annual | 5,125 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $30,340 | 798,359 | kWh | $0.04 |
Electricity Demand | $28,627 | 2,389 | kW-months/year | $11.98 |
Electricity Fees | $1,308 | - | $ | - |
Natural Gas | $121,397 | 34,047 | MMBtu | $3.57 |
TOTAL ENERGY COSTS | $187,739 | |||
RECOMMENDED SAVINGS* | $174,347 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $2,658 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.431 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY |
Savings: $153,750 Cost: $30,000 |
- | - | - | - | - | - | - | - | - | - | $153,750 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
$153,750 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1221 REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES |
Savings: $12,702 Cost: $42,000 |
- | - | - | - | $12,702 | 3,558 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$12,702 3,558 MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.3122 USE FILTRATION, CENTRIFUGING TO REMOVE CONTAMINANTS |
Savings: $2,744 Cost: $7,000 |
- | - | - | - | - | - | - | - | - | - | - | - | $2,744 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
$2,744 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $2,170 Cost: - |
$1,179 | 29,601 | $991 | 79 | - | - | - | - | - | - | - | - | - | - |
$1,179 29,601 kWh |
$991 79 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7144 INSTALL SPECTRAL REFLECTORS / DELAMP |
Savings: $1,422 Cost: - |
$968 | 24,326 | $454 | 36 | - | - | - | - | - | - | - | - | - | - |
$968 24,326 kWh |
$454 36 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.8142 DISTILL CONTAMINATED SOLVENTS FOR REUSE |
Savings: $1,071 Cost: $4,000 |
- | - | - | - | - | - | $1,937 | 280 | $(-124) | (-115) | $(-560) | - | $(-182) | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$1,937 280 gal |
$(-124) (-115) lb |
$(-560) - $ |
$(-182) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.8121 COVER CONTAINERS TO MINIMIZE EVAPORATIVE LOSSES |
Savings: $488 Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | $488 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
$488 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $174,347 Cost: $83,000 |
$2,147 | 53,927 | $1,445 | 115 | $12,702 | 3,558 | $1,937 | 280 | $(-124) | (-115) | $153,190 | - | $3,050 | - | $2,147 53,927 kWh |
$1,445 115 kW-months/year |
$12,702 3,558 MMBtu |
$1,937 280 gal |
$(-124) (-115) lb |
$153,190 - $ |
$3,050 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $2,658 Cost: - |
$1,179 | 29,601 | $991 | 79 | - | - | - | - | - | - | - | - | $488 | - | $1,179 29,601 kWh |
$991 79 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
$488 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost |