Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Wisconsin, Milwaukee |
---|---|
Assessment Year | 1998 |
Principal Product | Lead Castings |
NAICS | n/a |
SIC | 3053 - Gaskets, Packing And Sealing Devices |
Sales | $5,000,000-$10,000,000 |
# of Employees | 60 |
Plant Area (Sq.Ft.) | 50,000 |
Annual Production | 1,200,000 Pounds |
Production Hrs. Annual | 4,000 |
Location (State) | WI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $25,311 | 804,807 | kWh | $0.03 |
Electricity Demand | $29,636 | 3,489 | kW-months/year | $8.49 |
Electricity Fees | $3,759 | - | $ | - |
Natural Gas | $56,153 | 13,002 | MMBtu | $4.32 |
TOTAL ENERGY COSTS | $138,439 | |||
RECOMMENDED SAVINGS* | $69,243 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $53,129 |
#|Description |
Savings Cost |
Status | Electricity Demand | Natural Gas | Solid Waste (haz) | Personnel Changes | Administrative Changes | Electricity Demand | Natural Gas | Solid Waste (haz) | Personnel Changes | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.431 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY |
Savings: $45,000 Cost: - |
- | - | - | - | - | - | $45,000 | - | - | - |
- - kW-months/year |
- - MMBtu |
- - lb |
$45,000 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2426 USE WASTE HEAT FROM FLUE GASES TO HEAT SPACE CONDITIONING AIR |
Savings: $6,295 Cost: $11,500 |
- | - | $6,295 | 1,457 | - | - | - | - | - | - |
- - kW-months/year |
$6,295 1,457 MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.8113 PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER |
Savings: $6,880 Cost: $500 |
- | - | - | - | - | - | - | - | $6,880 | - |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
$6,880 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS |
Savings: $3,975 Cost: $8,500 |
- | - | - | - | $3,975 | - | - | - | - | - |
- - kW-months/year |
- - MMBtu |
$3,975 - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.7137 REPLACE CLOTH RAGS WITH PAPER TOWELS |
Savings: $1,218 Cost: - |
- | - | - | - | - | - | - | - | $1,218 | - |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
$1,218 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.3134 SHIFT FROM DAYTIME TO NIGHTTIME OPERATION |
Savings: $3,729 Cost: - |
$3,729 | 416 | - | - | - | - | - | - | - | - |
$3,729 416 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS |
Savings: $1,249 Cost: $300 |
$1,249 | 108 | - | - | - | - | - | - | - | - |
$1,249 108 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $897 Cost: $608 |
- | - | $897 | 208 | - | - | - | - | - | - |
- - kW-months/year |
$897 208 MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $69,243 Cost: $21,408 |
$4,978 | 524 | $7,192 | 1,665 | $3,975 | - | $45,000 | - | $8,098 | - | $4,978 524 kW-months/year |
$7,192 1,665 MMBtu |
$3,975 - lb |
$45,000 - $ |
$8,098 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $53,129 Cost: $800 |
$1,249 | 108 | - | - | - | - | $45,000 | - | $6,880 | - | $1,249 108 kW-months/year |
- - MMBtu |
- - lb |
$45,000 - $ |
$6,880 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Demand | Natural Gas | Solid Waste (haz) | Personnel Changes | Administrative Changes | Electricity Demand | Natural Gas | Solid Waste (haz) | Personnel Changes | Administrative Changes |