Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Wisconsin, Milwaukee |
---|---|
Assessment Year | 1999 |
Principal Product | Specialty Contract Furniture |
NAICS | n/a |
SIC | 2521 - Wood Office Furniture |
Sales | $10,000,000-$50,000,000 |
# of Employees | 190 |
Plant Area (Sq.Ft.) | 252,319 |
Annual Production | 14,000 Pieces |
Production Hrs. Annual | 2,375 |
Location (State) | WI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $100,613 | 3,885,991 | kWh | $0.03 |
Electricity Demand | $111,945 | 15,830 | kW-months/year | $7.07 |
Electricity Fees | $32,776 | - | $ | - |
Natural Gas | $87,875 | 25,444 | MMBtu | $3.45 |
TOTAL ENERGY COSTS | $362,674 | |||
RECOMMENDED SAVINGS* | $98,691 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $8,196 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Primary Raw Material | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Primary Raw Material | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | lb | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.2123 CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS |
Savings: $68,050 Cost: $1,000 |
- | - | - | - | - | - | - | - | - | - | - | - | - | - | $68,050 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
$68,050 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $11,924 Cost: $1,600 |
- | - | - | - | $11,924 | 3,456 | - | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$11,924 3,456 MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 4.445 INSTALL EQUIPMENT TO MOVE PRODUCT |
Savings: $5,222 Cost: $5,700 |
$(-3) | (-293) | $(-25) | (-3) | - | - | - | - | - | - | $5,250 | - | - | - | - | - |
$(-3) (-293) kWh |
$(-25) (-3) kW-months/year |
- - MMBtu |
- - gal |
- - lb |
$5,250 - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.8142 DISTILL CONTAMINATED SOLVENTS FOR REUSE |
Savings: $3,492 Cost: $6,000 |
- | - | - | - | - | - | $3,120 | 907 | $(-717) | (-435) | $(-1,271) | - | - | - | $2,360 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$3,120 907 gal |
$(-717) (-435) lb |
$(-1,271) - $ |
- - $ |
$2,360 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.3131 USE EVAPORATION TO CONCENTRATE MATERIAL |
Savings: $3,019 Cost: $10,000 |
- | - | - | - | $(-200) | (-58) | $4,096 | 6,072 | - | - | $(-877) | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$(-200) (-58) MMBtu |
$4,096 6,072 gal |
- - lb |
$(-877) - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7314 REDUCE VENTILATION AIR |
Savings: $2,871 Cost: $500 |
$536 | 19,637 | - | - | $2,335 | 677 | - | - | - | - | - | - | - | - | - | - |
$536 19,637 kWh |
- - kW-months/year |
$2,335 677 MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,551 Cost: - |
$803 | 29,601 | $748 | 101 | - | - | - | - | - | - | - | - | - | - | - | - |
$803 29,601 kWh |
$748 101 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4222 INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN |
Savings: $990 Cost: $5,024 |
$486 | 17,878 | $504 | 68 | - | - | - | - | - | - | - | - | - | - | - | - |
$486 17,878 kWh |
$504 68 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $433 Cost: $640 |
$224 | 8,206 | $209 | 28 | - | - | - | - | - | - | - | - | - | - | - | - |
$224 8,206 kWh |
$209 28 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.8112 COMBINE UTILITY METERS |
Savings: $562 Cost: $200 |
- | - | - | - | - | - | - | - | - | - | - | - | $562 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
$562 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $400 Cost: $809 |
$213 | 7,913 | $187 | 25 | - | - | - | - | - | - | - | - | - | - | - | - |
$213 7,913 kWh |
$187 25 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $177 Cost: $170 |
$97 | 3,517 | $80 | 11 | - | - | - | - | - | - | - | - | - | - | - | - |
$97 3,517 kWh |
$80 11 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $98,691 Cost: $31,643 |
$2,356 | 86,459 | $1,703 | 230 | $14,059 | 4,075 | $7,216 | 6,979 | $(-717) | (-435) | $3,102 | - | $562 | - | $70,410 | - | $2,356 86,459 kWh |
$1,703 230 kW-months/year |
$14,059 4,075 MMBtu |
$7,216 6,979 gal |
$(-717) (-435) lb |
$3,102 - $ |
$562 - $ |
$70,410 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $8,196 Cost: $11,364 |
$1,510 | 55,392 | $1,436 | 194 | - | - | - | - | - | - | $5,250 | - | - | - | - | - | $1,510 55,392 kWh |
$1,436 194 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
$5,250 - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | lb | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Primary Raw Material | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Primary Raw Material |