Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Wisconsin, Milwaukee |
---|---|
Assessment Year | 1999 |
Principal Product | Precision Molded Components |
NAICS | n/a |
SIC | 3089 - Plastics Products, Nec |
Sales | $5,000,000-$10,000,000 |
# of Employees | 67 |
Plant Area (Sq.Ft.) | 60,100 |
Annual Production | 0 Units |
Production Hrs. Annual | 6,000 |
Location (State) | WI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $87,742 | 2,219,519 | kWh | $0.04 |
Electricity Demand | $61,975 | 5,055 | kW-months/year | $12.26 |
Electricity Fees | $9,123 | - | $ | - |
Natural Gas | $6,718 | 1,301 | MMBtu | $5.16 |
TOTAL ENERGY COSTS | $172,917 | |||
RECOMMENDED SAVINGS* | $40,427 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Water Disposal | Administrative Changes | Electricity Usage | Electricity Demand | Water Disposal | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | Tgal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $15,106 Cost: - |
$15,106 | 364,009 | - | - | - | - | - | - |
$15,106 364,009 kWh |
- - kW-months/year |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $11,524 Cost: $20,900 |
$11,524 | 277,843 | - | - | - | - | - | - |
$11,524 277,843 kWh |
- - kW-months/year |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7251 REDUCE AIR CONDITIONING LOAD BY EVAPORATING WATER FROM ROOF |
Savings: $4,369 Cost: $7,590 |
$2,374 | 57,151 | $2,303 | 179 | $(-308) | (-68,400) | - | - |
$2,374 57,151 kWh |
$2,303 179 kW-months/year |
$(-308) (-68,400) Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $2,410 Cost: $7,200 |
$1,283 | 30,774 | $1,127 | 87 | - | - | - | - |
$1,283 30,774 kWh |
$1,127 87 kW-months/year |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,072 Cost: $210 |
$1,414 | 33,998 | $658 | 51 | - | - | - | - |
$1,414 33,998 kWh |
$658 51 kW-months/year |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $434 Cost: $640 |
$286 | 7,034 | $148 | 11 | - | - | - | - |
$286 7,034 kWh |
$148 11 kW-months/year |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2621 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE |
Savings: $1,906 Cost: $6,000 |
$1,210 | 29,015 | $696 | 54 | - | - | - | - |
$1,210 29,015 kWh |
$696 54 kW-months/year |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.7137 REPLACE CLOTH RAGS WITH PAPER TOWELS |
Savings: $1,671 Cost: - |
- | - | - | - | - | - | $1,671 | - |
- - kWh |
- - kW-months/year |
- - Tgal |
$1,671 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 4.232 LEASE EQUIPMENT INSTEAD OF PURCHASING |
Savings: $828 Cost: - |
- | - | - | - | - | - | $828 | - |
- - kWh |
- - kW-months/year |
- - Tgal |
$828 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS |
Savings: $107 Cost: - |
- | - | - | - | - | - | $107 | - |
- - kWh |
- - kW-months/year |
- - Tgal |
$107 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $40,427 Cost: $42,540 |
$33,197 | 799,824 | $4,932 | 382 | $(-308) | (-68,400) | $2,606 | - | $33,197 799,824 kWh |
$4,932 382 kW-months/year |
$(-308) (-68,400) Tgal |
$2,606 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | Tgal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Water Disposal | Administrative Changes | Electricity Usage | Electricity Demand | Water Disposal | Administrative Changes |