Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Wisconsin, Milwaukee |
---|---|
Assessment Year | 1999 |
Principal Product | Fabricated Metal Products |
NAICS | n/a |
SIC | 3499 - Fabricated Metal Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 90 |
Plant Area (Sq.Ft.) | 135,000 |
Annual Production | 4,000 Pieces |
Production Hrs. Annual | 5,650 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $94,218 | 2,226,553 | kWh | $0.04 |
Electricity Demand | $89,865 | 7,372 | kW-months/year | $12.19 |
Electricity Fees | $30,714 | - | $ | - |
Natural Gas | $30,401 | 5,571 | MMBtu | $5.46 |
TOTAL ENERGY COSTS | $268,114 | |||
RECOMMENDED SAVINGS* | $52,394 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $16,752 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Solid Waste (non-haz) | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Solid Waste (non-haz) | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.515 INSTALL SHELVES / RACKS TO UTILIZE UNUSED SPACE |
Savings: $19,500 Cost: $18,000 |
- | - | - | - | - | - | - | - | - | - | $19,500 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
$19,500 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL |
Savings: $7,993 Cost: - |
- | - | - | - | - | - | - | - | $7,993 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
$7,993 - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.8113 PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER |
Savings: $7,922 Cost: $500 |
- | - | - | - | $7,922 | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$7,922 - MMBtu |
- - Tgal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA |
Savings: $5,378 Cost: - |
- | - | - | - | $5,378 | 985 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$5,378 985 MMBtu |
- - Tgal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $4,145 Cost: $800 |
- | - | - | - | $4,145 | 759 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$4,145 759 MMBtu |
- - Tgal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.4154 ELIMINATE LEAKS IN WATER LINES AND VALVES |
Savings: $4,075 Cost: - |
- | - | - | - | - | - | $4,075 | 2,105,875 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$4,075 2,105,875 Tgal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $1,173 Cost: $1,920 |
$507 | 11,430 | $666 | 52 | - | - | - | - | - | - | - | - |
$507 11,430 kWh |
$666 52 kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $1,365 Cost: $4,374 |
$441 | 9,965 | $924 | 72 | - | - | - | - | - | - | - | - |
$441 9,965 kWh |
$924 72 kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS |
Savings: $843 Cost: $800 |
- | - | $843 | 66 | - | - | - | - | - | - | - | - |
- - kWh |
$843 66 kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $52,394 Cost: $26,394 |
$948 | 21,395 | $2,433 | 190 | $17,445 | 1,744 | $4,075 | 2,105,875 | $7,993 | - | $19,500 | - | $948 21,395 kWh |
$2,433 190 kW-months/year |
$17,445 1,744 MMBtu |
$4,075 2,105,875 Tgal |
$7,993 - lb |
$19,500 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $16,752 Cost: $7,094 |
$948 | 21,395 | $2,433 | 190 | $5,378 | 985 | - | - | $7,993 | - | - | - | $948 21,395 kWh |
$2,433 190 kW-months/year |
$5,378 985 MMBtu |
- - Tgal |
$7,993 - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Solid Waste (non-haz) | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Solid Waste (non-haz) | Personnel Changes |