Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Wisconsin, Milwaukee |
---|---|
Assessment Year | 1999 |
Principal Product | Commercial Printed Products |
NAICS | n/a |
SIC | 2752 - Commercial Printing, Lithographic |
Sales | $10,000,000-$50,000,000 |
# of Employees | 95 |
Plant Area (Sq.Ft.) | 40,000 |
Annual Production | 0 Units |
Production Hrs. Annual | 6,000 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $53,933 | 1,465,416 | kWh | $0.04 |
Electricity Demand | $69,776 | 5,628 | kW-months/year | $12.40 |
Electricity Fees | $16,693 | - | $ | - |
Natural Gas | $15,685 | 3,415 | MMBtu | $4.59 |
TOTAL ENERGY COSTS | $171,891 | |||
RECOMMENDED SAVINGS* | $10,770 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $3,454 Cost: $1,484 |
$2,092 | 53,634 | $1,362 | 104 | - | - | - | - |
$2,092 53,634 kWh |
$1,362 104 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $2,359 Cost: $7,200 |
$2,359 | 60,668 | - | - | - | - | - | - |
$2,359 60,668 kWh |
- - kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 4.445 INSTALL EQUIPMENT TO MOVE PRODUCT |
Savings: $1,875 Cost: $6,350 |
- | - | - | - | - | - | $1,875 | - |
- - kWh |
- - kW-months/year |
- - lb |
$1,875 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL |
Savings: $1,752 Cost: - |
- | - | - | - | $1,752 | - | - | - |
- - kWh |
- - kW-months/year |
$1,752 - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $689 Cost: $1,807 |
$304 | 7,913 | $385 | 29 | - | - | - | - |
$304 7,913 kWh |
$385 29 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $641 Cost: $640 |
$384 | 9,965 | $257 | 20 | - | - | - | - |
$384 9,965 kWh |
$257 20 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $10,770 Cost: $17,481 |
$5,139 | 132,180 | $2,004 | 153 | $1,752 | - | $1,875 | - | $5,139 132,180 kWh |
$2,004 153 kW-months/year |
$1,752 - lb |
$1,875 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes |