Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Wisconsin, Milwaukee |
---|---|
Assessment Year | 2000 |
Principal Product | Hydraulic, Water, and Air Hoses |
NAICS | n/a |
SIC | 3492 - Fluid Power Valves & Hose Fittings |
Sales | $10,000,000-$50,000,000 |
# of Employees | 110 |
Plant Area (Sq.Ft.) | 140,000 |
Annual Production | 30,000,000 Thousand Feet |
Production Hrs. Annual | 6,000 |
Location (State) | WI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $214,625 | 7,027,550 | kWh | $0.03 |
Electricity Demand | $106,689 | 16,546 | kW-months/year | $6.45 |
Electricity Fees | $28,950 | - | $ | - |
Natural Gas | $44,597 | 13,327 | MMBtu | $3.35 |
TOTAL ENERGY COSTS | $483,655 | |||
RECOMMENDED SAVINGS* | $24,436 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $3,598 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Water Disposal | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Water Disposal | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | Tgal | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $6,236 Cost: $1,860 |
$4,737 | 147,714 | $1,499 | 221 | - | - | - | - | - | - | - | - |
$4,737 147,714 kWh |
$1,499 221 kW-months/year |
- - Tgal |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $1,550 Cost: $740 |
$1,123 | 34,877 | $427 | 63 | - | - | - | - | - | - | - | - |
$1,123 34,877 kWh |
$427 63 kW-months/year |
- - Tgal |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $5,619 Cost: $16,000 |
$3,387 | 105,510 | $2,232 | 330 | - | - | - | - | - | - | - | - |
$3,387 105,510 kWh |
$2,232 330 kW-months/year |
- - Tgal |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.4114 REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER |
Savings: $3,741 Cost: $14,500 |
$(-384) | (-12,016) | $(-163) | (-24) | $4,788 | 5,832,000 | - | - | $(-500) | - | - | - |
$(-384) (-12,016) kWh |
$(-163) (-24) kW-months/year |
$4,788 5,832,000 Tgal |
- - lb |
$(-500) - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.4113 TREAT AND REUSE RINSE WATERS |
Savings: $3,598 Cost: $6,375 |
- | - | - | - | $5,098 | 6,210,000 | - | - | - | - | $(-1,500) | - |
- - kWh |
- - kW-months/year |
$5,098 6,210,000 Tgal |
- - lb |
- - $ |
$(-1,500) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $2,130 Cost: $2,150 |
$1,414 | 43,962 | $716 | 106 | - | - | - | - | - | - | - | - |
$1,414 43,962 kWh |
$716 106 kW-months/year |
- - Tgal |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.5218 REUSE / RECYCLE/ SELL RUBBER PRODUCTS |
Savings: $1,562 Cost: - |
- | - | - | - | - | - | $1,562 | 83,200 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - Tgal |
$1,562 83,200 lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $24,436 Cost: $41,625 |
$10,277 | 320,047 | $4,711 | 696 | $9,886 | 12,042,000 | $1,562 | 83,200 | $(-500) | - | $(-1,500) | - | $10,277 320,047 kWh |
$4,711 696 kW-months/year |
$9,886 12,042,000 Tgal |
$1,562 83,200 lb |
$(-500) - $ |
$(-1,500) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $3,598 Cost: $6,375 |
- | - | - | - | $5,098 | 6,210,000 | - | - | - | - | $(-1,500) | - | - - kWh |
- - kW-months/year |
$5,098 6,210,000 Tgal |
- - lb |
- - $ |
$(-1,500) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | Tgal | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Water Disposal | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Water Disposal | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost |