IAC Assessment: WI0383
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: WI0383
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Wisconsin, Milwaukee
Assessment Year 2000
Principal Product Canned Vegetables
NAICS n/a
SIC 2033 - Canned Fruits And Vegetables
Sales $10,000,000-$50,000,000
# of Employees 210
Plant Area (Sq.Ft.) 222,810
Annual Production 4,500,000 Pieces
Production Hrs. Annual 4,250
Location (State) WI
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $86,365 4,195,193 kWh $0.02
Electricity Demand $86,858 9,833 kW-months/year $8.83
Electricity Fees $16,474 - $ -
Natural Gas $432,410 122,953 MMBtu $3.52
TOTAL ENERGY COSTS $898,982
RECOMMENDED SAVINGS* $73,662 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $13,695
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz)
$ kWh $ kW-months/year $ MMBtu $ lb
01: 2.2449 RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER Savings:
$41,291
Cost:
$72,000
- - - - $41,291 11,731 - - -
-
kWh
-
-
kW-months/year
$41,291
11,731
MMBtu
-
-
lb
02: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$14,801
Cost:
$20,000
- - - - $14,801 4,205 - - -
-
kWh
-
-
kW-months/year
$14,801
4,205
MMBtu
-
-
lb
03: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$7,946
Cost:
$22,500
- - - - $7,946 2,257 - - -
-
kWh
-
-
kW-months/year
$7,946
2,257
MMBtu
-
-
lb
04: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS Savings:
$4,492
Cost:
$11,550
- - $4,492 378 - - - - -
-
kWh
$4,492
378
kW-months/year
-
-
MMBtu
-
-
lb
05: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS Savings:
$3,875
Cost:
-
- - - - - - $3,875 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$3,875
-
lb
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$1,257
Cost:
$740
$592 27,550 $665 72 - - - - $592
27,550
kWh
$665
72
kW-months/year
-
-
MMBtu
-
-
lb
TOTAL RECOMMENDED Savings:
$73,662
Cost:
$126,790
$592 27,550 $5,157 450 $64,038 18,193 $3,875 - $592
27,550
kWh
$5,157
450
kW-months/year
$64,038
18,193
MMBtu
$3,875
-
lb
TOTAL IMPLEMENTED Savings:
$13,695
Cost:
$34,790
$592 27,550 $5,157 450 $7,946 2,257 - - $592
27,550
kWh
$5,157
450
kW-months/year
$7,946
2,257
MMBtu
-
-
lb
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ lb
Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz)