Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Wisconsin, Milwaukee |
---|---|
Assessment Year | 2003 |
Principal Product | Industrial Machining |
NAICS | 332710 - Machine Shops |
SIC | 3599 - Industrial Machinery, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 90 |
Plant Area (Sq.Ft.) | 36,000 |
Annual Production | 1,200,000 Pieces |
Production Hrs. Annual | 6,000 |
Location (State) | WI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $61,894 | 1,478,883 | kWh | $0.04 |
Electricity Demand | $27,659 | 2,811 | kW-months/year | $9.84 |
Electricity Fees | $34,693 | - | $ | - |
Natural Gas | $3,026 | 478 | MMBtu | $6.33 |
TOTAL ENERGY COSTS | $136,472 | |||
RECOMMENDED SAVINGS* | $22,943 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $11,769 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.6112 USE FILTER AND DRYING OVEN TO REDUCE SLUDGE VOLUME |
Savings: $6,597 Cost: $9,000 |
- | - | - | - | $(-283) | (-45) | $8,280 | 5,963 | $(-1,400) | - |
- - kWh |
- - kW-months/year |
$(-283) (-45) MMBtu |
$8,280 5,963 gal |
$(-1,400) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $4,807 Cost: $7,500 |
$4,807 | 108,767 | - | - | - | - | - | - | - | - |
$4,807 108,767 kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $4,189 Cost: $8,655 |
$2,779 | 62,874 | $1,410 | 129 | - | - | - | - | - | - |
$2,779 62,874 kWh |
$1,410 129 kW-months/year |
- - MMBtu |
- - gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $3,383 Cost: $2,000 |
- | - | - | - | $3,383 | 534 | - | - | - | - |
- - kWh |
- - kW-months/year |
$3,383 534 MMBtu |
- - gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $2,301 Cost: $1,424 |
- | - | - | - | $2,301 | 364 | - | - | - | - |
- - kWh |
- - kW-months/year |
$2,301 364 MMBtu |
- - gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $983 Cost: $740 |
$717 | 16,223 | $266 | 24 | - | - | - | - | - | - |
$717 16,223 kWh |
$266 24 kW-months/year |
- - MMBtu |
- - gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $683 Cost: $600 |
- | - | - | - | $683 | 108 | - | - | - | - |
- - kWh |
- - kW-months/year |
$683 108 MMBtu |
- - gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $22,943 Cost: $29,919 |
$8,303 | 187,864 | $1,676 | 153 | $6,084 | 961 | $8,280 | 5,963 | $(-1,400) | - | $8,303 187,864 kWh |
$1,676 153 kW-months/year |
$6,084 961 MMBtu |
$8,280 5,963 gal |
$(-1,400) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $11,769 Cost: $18,395 |
$3,496 | 79,097 | $1,676 | 153 | $(-283) | (-45) | $8,280 | 5,963 | $(-1,400) | - | $3,496 79,097 kWh |
$1,676 153 kW-months/year |
$(-283) (-45) MMBtu |
$8,280 5,963 gal |
$(-1,400) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | Personnel Changes |