Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Wisconsin, Milwaukee |
---|---|
Assessment Year | 2003 |
Principal Product | 35000 |
NAICS | 326199 - All Other Plastics Product Manufacturing |
SIC | 3089 - Plastics Products, Nec |
Sales | $100,000,000-$500,000,000 |
# of Employees | 600 |
Plant Area (Sq.Ft.) | 295,000 |
Annual Production | 70,000,000 Pounds |
Production Hrs. Annual | 8,400 |
Location (State) | WI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,362,009 | 46,937,747 | kWh | $0.03 |
Electricity Demand | $446,589 | 75,358 | kW-months/year | $5.93 |
Electricity Fees | $325,646 | - | $ | - |
Natural Gas | $506,120 | 96,045 | MMBtu | $5.27 |
TOTAL ENERGY COSTS | $2,660,873 | |||
RECOMMENDED SAVINGS* | $58,734 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Personnel Changes | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | Tgal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $21,502 Cost: $30,000 |
$21,502 | 704,970 | - | - | - | - | - | - | - | - | - | - |
$21,502 704,970 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.3132 USE REVERSE OSMOSIS TO CONCENTRATE MATERIAL |
Savings: $14,092 Cost: $36,000 |
$(-2,500) | (-81,967) | - | - | - | - | - | - | $17,242 | 8,306,000 | $(-650) | - |
$(-2,500) (-81,967) kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$17,242 8,306,000 Tgal |
$(-650) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $9,847 Cost: $3,433 |
$8,229 | 269,803 | $1,618 | 260 | - | - | - | - | - | - | - | - |
$8,229 269,803 kWh |
$1,618 260 kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $3,486 Cost: $500 |
- | - | - | - | - | - | $3,486 | 662 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$3,486 662 MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $7,048 Cost: $1,280 |
$5,773 | 189,274 | $1,275 | 205 | - | - | - | - | - | - | - | - |
$5,773 189,274 kWh |
$1,275 205 kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS |
Savings: $2,005 Cost: $1,400 |
- | - | $1,670 | 269 | $335 | - | - | - | - | - | - | - |
- - kWh |
$1,670 269 kW-months/year |
$335 - $ |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $754 Cost: $294 |
- | - | - | - | - | - | $754 | 143 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$754 143 MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $58,734 Cost: $72,907 |
$33,004 | 1,082,080 | $4,563 | 734 | $335 | - | $4,240 | 805 | $17,242 | 8,306,000 | $(-650) | - | $33,004 1,082,080 kWh |
$4,563 734 kW-months/year |
$335 - $ |
$4,240 805 MMBtu |
$17,242 8,306,000 Tgal |
$(-650) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | Tgal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Personnel Changes | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Personnel Changes |