Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Wisconsin, Milwaukee |
---|---|
Assessment Year | 2003 |
Principal Product | Sintered metal products |
NAICS | 332117 - Powder Metallurgy Part Manufacturing |
SIC | 3399 - Primary Metal Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 150 |
Plant Area (Sq.Ft.) | 75,000 |
Annual Production | 5,200,000 Pounds |
Production Hrs. Annual | 6,000 |
Location (State) | WI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $211,545 | 7,108,800 | kWh | $0.03 |
Electricity Demand | $126,026 | 13,448 | kW-months/year | $9.37 |
Electricity Fees | $25,193 | - | $ | - |
Natural Gas | $104,829 | 15,233 | MMBtu | $6.88 |
TOTAL ENERGY COSTS | $561,245 | |||
RECOMMENDED SAVINGS* | $123,806 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Other Liquid (haz) | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Other Liquid (haz) | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | gal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.4114 REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER |
Savings: $54,337 Cost: $72,000 |
$(-13,743) | (-268,560) | - | - | - | - | $68,080 | 28,970,000 | - | - | - | - |
$(-13,743) (-268,560) kWh |
- - kW-months/year |
- - MMBtu |
$68,080 28,970,000 Tgal |
- - gal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.6124 BURN WASTE OIL FOR HEAT |
Savings: $44,636 Cost: $30,000 |
$(-1,326) | (-14,089) | - | - | $23,962 | 3,483 | - | - | $22,000 | 20,000 | - | - |
$(-1,326) (-14,089) kWh |
- - kW-months/year |
$23,962 3,483 MMBtu |
- - Tgal |
$22,000 20,000 gal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $5,692 Cost: $12,000 |
$5,692 | 181,278 | - | - | - | - | - | - | - | - | - | - |
$5,692 181,278 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $4,850 Cost: $2,700 |
$3,463 | 110,278 | $1,387 | 140 | - | - | - | - | - | - | - | - |
$3,463 110,278 kWh |
$1,387 140 kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.7137 REPLACE CLOTH RAGS WITH PAPER TOWELS |
Savings: $4,710 Cost: - |
- | - | - | - | - | - | - | - | - | - | $4,710 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
$4,710 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $4,063 Cost: $1,000 |
- | - | - | - | $4,063 | 591 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$4,063 591 MMBtu |
- - Tgal |
- - gal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,926 Cost: $8,580 |
$2,400 | 76,440 | $1,526 | 153 | - | - | - | - | - | - | - | - |
$2,400 76,440 kWh |
$1,526 153 kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2515 USE OPTIMUM THICKNESS INSULATION |
Savings: $1,592 Cost: $687 |
$1,081 | 34,434 | $511 | 52 | - | - | - | - | - | - | - | - |
$1,081 34,434 kWh |
$511 52 kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $123,806 Cost: $126,967 |
$(-2,433) | 119,781 | $3,424 | 345 | $28,025 | 4,074 | $68,080 | 28,970,000 | $22,000 | 20,000 | $4,710 | - | $(-2,433) 119,781 kWh |
$3,424 345 kW-months/year |
$28,025 4,074 MMBtu |
$68,080 28,970,000 Tgal |
$22,000 20,000 gal |
$4,710 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | gal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Other Liquid (haz) | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Other Liquid (haz) | Ancillary Material Cost |