Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Wisconsin, Milwaukee |
---|---|
Assessment Year | 2005 |
Principal Product | Laminated Plastics |
NAICS | 326199 - All Other Plastics Product Manufacturing |
SIC | 3089 - Plastics Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 150 |
Plant Area (Sq.Ft.) | 134,000 |
Annual Production | 4,000 Tons |
Production Hrs. Annual | 8,160 |
Location (State) | WI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $249,578 | 7,511,280 | kWh | $0.03 |
Electricity Demand | $207,557 | 19,447 | kW-months/year | $10.67 |
Electricity Fees | $78,476 | - | $ | - |
Natural Gas | $224,524 | 27,711 | MMBtu | $8.10 |
TOTAL ENERGY COSTS | $771,135 | |||
RECOMMENDED SAVINGS* | $46,794 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $26,079 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $14,385 Cost: $25,200 |
$9,768 | 279,888 | $4,617 | 411 | - | - | - | - | - | - |
$9,768 279,888 kWh |
$4,617 411 kW-months/year |
- - MMBtu |
- - gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.3131 USE EVAPORATION TO CONCENTRATE MATERIAL |
Savings: $10,448 Cost: $8,000 |
- | - | - | - | $(-522) | (-65) | $10,970 | 3,557 | - | - |
- - kWh |
- - kW-months/year |
$(-522) (-65) MMBtu |
$10,970 3,557 gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $6,782 Cost: $4,300 |
$3,319 | 95,115 | - | - | $3,463 | 428 | - | - | - | - |
$3,319 95,115 kWh |
- - kW-months/year |
$3,463 428 MMBtu |
- - gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 4.431 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY |
Savings: $5,832 Cost: $1,000 |
- | - | - | - | - | - | - | - | $5,832 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
$5,832 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4312 IMPROVE LUBRICATION PRACTICES |
Savings: $3,033 Cost: $2,155 |
$2,061 | 59,037 | $972 | 87 | - | - | - | - | - | - |
$2,061 59,037 kWh |
$972 87 kW-months/year |
- - MMBtu |
- - gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7442 KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE |
Savings: $2,820 Cost: - |
- | - | - | - | $2,820 | 348 | - | - | - | - |
- - kWh |
- - kW-months/year |
$2,820 348 MMBtu |
- - gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $1,494 Cost: $600 |
- | - | - | - | $1,494 | 184 | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,494 184 MMBtu |
- - gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $1,335 Cost: $1,280 |
$875 | 25,079 | $460 | 41 | - | - | - | - | - | - |
$875 25,079 kWh |
$460 41 kW-months/year |
- - MMBtu |
- - gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $665 Cost: $800 |
$665 | 19,054 | - | - | - | - | - | - | - | - |
$665 19,054 kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $46,794 Cost: $43,335 |
$16,688 | 478,173 | $6,049 | 539 | $7,255 | 895 | $10,970 | 3,557 | $5,832 | - | $16,688 478,173 kWh |
$6,049 539 kW-months/year |
$7,255 895 MMBtu |
$10,970 3,557 gal |
$5,832 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $26,079 Cost: $30,235 |
$12,704 | 364,004 | $6,049 | 539 | $1,494 | 184 | - | - | $5,832 | - | $12,704 364,004 kWh |
$6,049 539 kW-months/year |
$1,494 184 MMBtu |
- - gal |
$5,832 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | One-time Revenue or Avoided Cost |