IAC Assessment: WM0050
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: WM0050
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Wisconsin, Milwaukee
Assessment Year 2014
Principal Product wood products
NAICS 321211 - Hardwood Veneer and Plywood Manufacturing
SIC 2435 - Hardwood Veneer And Plywood
Sales $10,000,000-$50,000,000
# of Employees 177
Plant Area (Sq.Ft.) 250,000
Annual Production 50,000 Pieces
Production Hrs. Annual 3,536
Location (State) WI
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $251,154 4,223,900 kWh $0.06
Electricity Demand $122,365 14,433 kW-months/year $8.48
Electricity Fees $52,126 - $ -
Natural Gas $502,679 81,651 MMBtu $6.16
TOTAL ENERGY COSTS $1,029,642
RECOMMENDED SAVINGS* $61,867 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Solid Waste (non-haz) Ancillary Material Cost Electricity Usage Electricity Demand Solid Waste (non-haz) Ancillary Material Cost
$ kWh $ kW-months/year $ lb $ $
01: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$6,104
Cost:
$8,000
- - $6,104 720 - - - - -
-
kWh
$6,104
720
kW-months/year
-
-
lb
-
-
$
02: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$357
Cost:
-
$357 6,006 - - - - - - $357
6,006
kWh
-
-
kW-months/year
-
-
lb
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,875
Cost:
$1,800
$501 8,430 $274 32 - - $2,100 - $501
8,430
kWh
$274
32
kW-months/year
-
-
lb
$2,100
-
$
04: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$8,029
Cost:
-
$8,029 135,031 - - - - - - $8,029
135,031
kWh
-
-
kW-months/year
-
-
lb
-
-
$
05: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$887
Cost:
$1,575
$887 14,923 - - - - - - $887
14,923
kWh
-
-
kW-months/year
-
-
lb
-
-
$
06: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$3,302
Cost:
$2,100
$2,225 37,425 $1,077 127 - - - - $2,225
37,425
kWh
$1,077
127
kW-months/year
-
-
lb
-
-
$
07: 3.6125 SELL COMBUSTIBLE WASTE Savings:
$39,202
Cost:
$97,000
- - - - $39,202 226,066 - - -
-
kWh
-
-
kW-months/year
$39,202
226,066
lb
-
-
$
08: 2.4224 UPGRADE CONTROLS ON COMPRESSORS Savings:
$1,111
Cost:
-
$1,111 18,689 - - - - - - $1,111
18,689
kWh
-
-
kW-months/year
-
-
lb
-
-
$
TOTAL RECOMMENDED Savings:
$61,867
Cost:
$110,475
$13,110 220,504 $7,455 879 $39,202 226,066 $2,100 - $13,110
220,504
kWh
$7,455
879
kW-months/year
$39,202
226,066
lb
$2,100
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
lb
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ lb $ $
Electricity Usage Electricity Demand Solid Waste (non-haz) Ancillary Material Cost Electricity Usage Electricity Demand Solid Waste (non-haz) Ancillary Material Cost