Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | West Virginia University |
---|---|
Assessment Year | 2010 |
Principal Product | Automotive Stampings |
NAICS | 336370 - Motor Vehicle Metal Stamping |
SIC | 3465 - Automotive Stampings |
Sales | $10,000,000-$50,000,000 |
# of Employees | 160 |
Plant Area (Sq.Ft.) | 250,000 |
Annual Production | 64,000,000 Pounds |
Production Hrs. Annual | 6,000 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $586,322 | 8,652,000 | kWh | $0.07 |
Electricity Demand | $184,170 | 23,021 | kW-months/year | $8.00 |
Natural Gas | $192,665 | 18,667 | MMBtu | $10.32 |
TOTAL ENERGY COSTS | $963,157 | |||
RECOMMENDED SAVINGS* | $186,106 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $42,699 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $86,422 Cost: $15,000 |
$154,330 | 2,276,255 | $46,272 | 5,784 | $(-114,180) | (-11,064) | - | - |
$154,330 2,276,255 kWh |
$46,272 5,784 kW-months/year |
$(-114,180) (-11,064) MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $21,876 Cost: $30,800 |
$18,468 | 272,394 | $3,408 | 426 | - | - | - | - |
$18,468 272,394 kWh |
$3,408 426 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7314 REDUCE VENTILATION AIR |
Savings: $18,153 Cost: $5,000 |
- | - | - | - | $18,153 | 1,759 | - | - |
- - kWh |
- - kW-months/year |
$18,153 1,759 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3191 USE DEMAND CONTROLLER OR LOAD SHEDDER |
Savings: $14,296 Cost: $7,820 |
- | - | $14,296 | 1,787 | - | - | - | - |
- - kWh |
$14,296 1,787 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7231 USE RADIANT HEATER FOR SPOT HEATING |
Savings: $12,353 Cost: $34,050 |
- | - | - | - | $12,353 | 1,197 | - | - |
- - kWh |
- - kW-months/year |
$12,353 1,197 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $8,767 Cost: $1,503 |
$7,095 | 104,649 | $1,672 | 209 | - | - | - | - |
$7,095 104,649 kWh |
$1,672 209 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $7,621 Cost: $2,000 |
$6,173 | 91,045 | $1,448 | 181 | - | - | - | - |
$6,173 91,045 kWh |
$1,448 181 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4157 ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM |
Savings: $5,733 Cost: $700 |
$4,736 | 69,850 | $1,120 | 140 | - | - | $(-123) | - |
$4,736 69,850 kWh |
$1,120 140 kW-months/year |
- - MMBtu |
$(-123) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7316 CENTRALIZE CONTROL OF EXHAUST FANS TO ENSURE THEIR SHUTDOWN, OR ESTABLISH PROGRAM TO ENSURE MANUAL SHUTDOWN |
Savings: $4,603 Cost: $5,265 |
- | - | - | - | $4,603 | 446 | - | - |
- - kWh |
- - kW-months/year |
$4,603 446 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $3,852 Cost: $884 |
$3,116 | 45,958 | $736 | 92 | - | - | - | - |
$3,116 45,958 kWh |
$736 92 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,398 Cost: $4,490 |
$870 | 12,825 | $528 | 66 | - | - | - | - |
$870 12,825 kWh |
$528 66 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $1,032 Cost: $1,312 |
- | - | - | - | $1,032 | 100 | - | - |
- - kWh |
- - kW-months/year |
$1,032 100 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $186,106 Cost: $108,824 |
$194,788 | 2,872,976 | $69,480 | 8,685 | $(-78,039) | (-7,562) | $(-123) | - | $194,788 2,872,976 kWh |
$69,480 8,685 kW-months/year |
$(-78,039) (-7,562) MMBtu |
$(-123) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $42,699 Cost: $18,709 |
$21,990 | 324,327 | $19,800 | 2,475 | $1,032 | 100 | $(-123) | - | $21,990 324,327 kWh |
$19,800 2,475 kW-months/year |
$1,032 100 MMBtu |
$(-123) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes |