IAC Assessment: WV0450
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: WV0450
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center West Virginia University
Assessment Year 2012
Principal Product coal tar pitch and creosote solutions
NAICS 325194 - Cyclic Crude, Intermediate, and Gum and Wood Chemical Manufacturing
SIC 2865 - Cyclic Crudes And Intermediates
Sales $50,000,000-$100,000,000
# of Employees 55
Plant Area (Sq.Ft.) 696,960
Annual Production 187,393 Tons
Production Hrs. Annual 8,760
Location (State) PA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $731,248 11,541,000 kWh $0.06
Natural Gas $1,287,994 200,931 MMBtu $6.41
Other Energy $2,233,606 300,388 MMBtu $7.44
TOTAL ENERGY COSTS $4,252,848
RECOMMENDED SAVINGS* $740,671 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $333,287
#|Description Savings
Cost
Status Electricity Usage Natural Gas Other Energy Personnel Changes Administrative Changes Electricity Usage Natural Gas Other Energy Personnel Changes Administrative Changes
$ kWh $ MMBtu $ MMBtu $ $ $ $
01: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$173,557
Cost:
$1,000
- - $173,737 27,104 - - $(-180) - - - -
-
kWh
$173,737
27,104
MMBtu
-
-
MMBtu
$(-180)
-
$
-
-
$
02: 2.2422 USE WASTE HEAT FROM HOT FLUE GASES TO GENERATE STEAM Savings:
$141,590
Cost:
$210,000
- - - - $146,590 19,703 $(-5,000) - - - -
-
kWh
-
-
MMBtu
$146,590
19,703
MMBtu
$(-5,000)
-
$
-
-
$
03: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$130,899
Cost:
$157,320
- - $130,899 20,421 - - - - - - -
-
kWh
$130,899
20,421
MMBtu
-
-
MMBtu
-
-
$
-
-
$
04: 2.5194 REDESIGN PROCESS Savings:
$102,043
Cost:
$230,000
$(-7,584) (-119,701) $32,198 5,023 $89,399 12,016 - - $(-11,970) - $(-7,584)
(-119,701)
kWh
$32,198
5,023
MMBtu
$89,399
12,016
MMBtu
-
-
$
$(-11,970)
-
$
05: 2.3412 USE WASTE HEAT TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR Savings:
$97,121
Cost:
$400,000
$107,121 1,690,680 - - - - $(-10,000) - - - $107,121
1,690,680
kWh
-
-
MMBtu
-
-
MMBtu
$(-10,000)
-
$
-
-
$
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$36,667
Cost:
$21,800
$36,667 578,708 - - - - - - - - $36,667
578,708
kWh
-
-
MMBtu
-
-
MMBtu
-
-
$
-
-
$
07: 2.7132 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS Savings:
$11,389
Cost:
$6,500
$11,389 179,755 - - - - - - - - $11,389
179,755
kWh
-
-
MMBtu
-
-
MMBtu
-
-
$
-
-
$
08: 2.4157 ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM Savings:
$10,199
Cost:
$1,000
$11,812 186,420 - - - - $(-1,613) - - - $11,812
186,420
kWh
-
-
MMBtu
-
-
MMBtu
$(-1,613)
-
$
-
-
$
09: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$9,686
Cost:
$21,120
- - $9,686 1,511 - - - - - - -
-
kWh
$9,686
1,511
MMBtu
-
-
MMBtu
-
-
$
-
-
$
10: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$8,953
Cost:
$18,267
$8,953 141,305 - - - - - - - - $8,953
141,305
kWh
-
-
MMBtu
-
-
MMBtu
-
-
$
-
-
$
11: 2.4151 DEVELOP A REPAIR/REPLACE POLICY Savings:
$8,489
Cost:
$1,210
$9,449 149,140 - - - - $(-960) - - - $9,449
149,140
kWh
-
-
MMBtu
-
-
MMBtu
$(-960)
-
$
-
-
$
12: 2.7241 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT Savings:
$7,314
Cost:
$3,360
$7,314 115,442 - - - - - - - - $7,314
115,442
kWh
-
-
MMBtu
-
-
MMBtu
-
-
$
-
-
$
13: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$2,764
Cost:
$1,800
$2,764 43,627 - - - - - - - - $2,764
43,627
kWh
-
-
MMBtu
-
-
MMBtu
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$740,671
Cost:
$1,073,377
$187,885 2,965,376 $346,520 54,059 $235,989 31,719 $(-17,753) - $(-11,970) - $187,885
2,965,376
kWh
$346,520
54,059
MMBtu
$235,989
31,719
MMBtu
$(-17,753)
-
$
$(-11,970)
-
$
TOTAL IMPLEMENTED Savings:
$333,287
Cost:
$184,297
$29,791 470,200 $304,636 47,525 - - $(-1,140) - - - $29,791
470,200
kWh
$304,636
47,525
MMBtu
-
-
MMBtu
$(-1,140)
-
$
-
-
$
Savings
Cost
$ kWh $ MMBtu $ MMBtu $ $ $ $
Electricity Usage Natural Gas Other Energy Personnel Changes Administrative Changes Electricity Usage Natural Gas Other Energy Personnel Changes Administrative Changes