IAC Assessment: WV0493
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: WV0493
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center West Virginia University
Assessment Year 2014
Principal Product polymer pellets
NAICS 325211 - Plastics Material and Resin Manufacturing
SIC 2821 - Plastics Materials And Resins
Sales $1,000,000-$5,000,000
# of Employees 63
Plant Area (Sq.Ft.) 217,000
Annual Production 4,800,000 Pounds
Production Hrs. Annual 8,568
Location (State) WV
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $300,498 7,924,800 kWh $0.04
Electricity Demand $260,973 19,760 kW-months/year $13.21
Electricity Fees $12,225 - $ -
TOTAL ENERGY COSTS $573,696
RECOMMENDED SAVINGS* $99,870 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $91,318
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Personnel Changes Electricity Usage Electricity Demand Personnel Changes
$ kWh $ kW-months/year $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$40,956
Cost:
$44,486
$27,891 706,102 $13,065 989 - - $27,891
706,102
kWh
$13,065
989
kW-months/year
-
-
$
02: 2.3191 USE DEMAND CONTROLLER OR LOAD SHEDDER Savings:
$19,168
Cost:
$5,300
- - $19,168 1,451 - - -
-
kWh
$19,168
1,451
kW-months/year
-
-
$
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$8,848
Cost:
$509
$6,021 152,443 $2,827 214 - - $6,021
152,443
kWh
$2,827
214
kW-months/year
-
-
$
04: 2.4157 ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM Savings:
$5,786
Cost:
$1,000
$4,983 126,160 $2,338 177 $(-1,535) - $4,983
126,160
kWh
$2,338
177
kW-months/year
$(-1,535)
-
$
05: 2.4224 UPGRADE CONTROLS ON COMPRESSORS Savings:
$5,218
Cost:
$10,000
$3,554 89,964 $1,664 126 - - $3,554
89,964
kWh
$1,664
126
kW-months/year
-
-
$
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$5,192
Cost:
$7,244
$3,237 81,945 $1,955 148 - - $3,237
81,945
kWh
$1,955
148
kW-months/year
-
-
$
07: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$5,090
Cost:
-
$3,465 87,719 $1,625 123 - - $3,465
87,719
kWh
$1,625
123
kW-months/year
-
-
$
08: 2.2511 INSULATE BARE EQUIPMENT Savings:
$3,507
Cost:
$1,251
$2,384 60,358 $1,123 85 - - $2,384
60,358
kWh
$1,123
85
kW-months/year
-
-
$
09: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$2,643
Cost:
$15
$1,798 45,508 $845 64 - - $1,798
45,508
kWh
$845
64
kW-months/year
-
-
$
10: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE Savings:
$2,071
Cost:
$1,000
$1,410 35,690 $661 50 - - $1,410
35,690
kWh
$661
50
kW-months/year
-
-
$
11: 2.4151 DEVELOP A REPAIR/REPLACE POLICY Savings:
$1,391
Cost:
$661
$1,196 30,278 $555 42 $(-360) - $1,196
30,278
kWh
$555
42
kW-months/year
$(-360)
-
$
TOTAL RECOMMENDED Savings:
$99,870
Cost:
$71,466
$55,939 1,416,167 $45,826 3,469 $(-1,895) - $55,939
1,416,167
kWh
$45,826
3,469
kW-months/year
$(-1,895)
-
$
TOTAL IMPLEMENTED Savings:
$91,318
Cost:
$69,805
$49,868 1,262,480 $42,985 3,254 $(-1,535) - $49,868
1,262,480
kWh
$42,985
3,254
kW-months/year
$(-1,535)
-
$
Savings
Cost
$ kWh $ kW-months/year $ $
Electricity Usage Electricity Demand Personnel Changes Electricity Usage Electricity Demand Personnel Changes