IAC Assessment: WV0501
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: WV0501
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center West Virginia University
Assessment Year 2015
Principal Product Hardwood Lumber
NAICS 321912 - Cut Stock, Resawing Lumber, and Planing
SIC 2421 - Sawmills And Planing Mills, General
Sales $10,000,000-$50,000,000
# of Employees 30
Plant Area (Sq.Ft.) 200,000
Annual Production 1,400,000 Pieces
Production Hrs. Annual 2,040
Location (State) WV
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $179,728 3,166,800 kWh $0.06
Electricity Demand $29,827 6,520 kW-months/year $4.57
Wood $233,600 116,800 MMBtu $2.00
TOTAL ENERGY COSTS $443,155
RECOMMENDED SAVINGS* $38,352 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $13,280
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Wood Personnel Changes Electricity Usage Electricity Demand Wood Personnel Changes
$ kWh $ kW-months/year $ MMBtu $ $
01: 2.1116 IMPROVE COMBUSTION CONTROL CAPABILITY Savings:
$12,166
Cost:
$24,000
- - - - $12,166 6,083 - - -
-
kWh
-
-
kW-months/year
$12,166
6,083
MMBtu
-
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$6,534
Cost:
$26,699
$4,436 78,100 $2,098 459 - - - - $4,436
78,100
kWh
$2,098
459
kW-months/year
-
-
MMBtu
-
-
$
03: 2.4157 ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM Savings:
$5,928
Cost:
$1,000
$5,718 100,675 $2,705 592 - - $(-2,495) - $5,718
100,675
kWh
$2,705
592
kW-months/year
-
-
MMBtu
$(-2,495)
-
$
04: 2.2113 REPAIR OR REPLACE STEAM TRAPS Savings:
$3,486
Cost:
$5,200
- - - - $3,686 1,843 $(-200) - -
-
kWh
-
-
kW-months/year
$3,686
1,843
MMBtu
$(-200)
-
$
05: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$3,359
Cost:
-
$2,280 40,143 $1,079 236 - - - - $2,280
40,143
kWh
$1,079
236
kW-months/year
-
-
MMBtu
-
-
$
06: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS Savings:
$2,432
Cost:
$400
- - - - $2,432 1,216 - - -
-
kWh
-
-
kW-months/year
$2,432
1,216
MMBtu
-
-
$
07: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$1,751
Cost:
$7,185
$1,189 20,940 $562 123 - - - - $1,189
20,940
kWh
$562
123
kW-months/year
-
-
MMBtu
-
-
$
08: 2.2511 INSULATE BARE EQUIPMENT Savings:
$1,262
Cost:
$2,533
- - - - $1,262 631 - - -
-
kWh
-
-
kW-months/year
$1,262
631
MMBtu
-
-
$
09: 2.4151 DEVELOP A REPAIR/REPLACE POLICY Savings:
$1,062
Cost:
$649
$965 16,989 $457 100 - - $(-360) - $965
16,989
kWh
$457
100
kW-months/year
-
-
MMBtu
$(-360)
-
$
10: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$372
Cost:
$327
$253 4,450 $119 26 - - - - $253
4,450
kWh
$119
26
kW-months/year
-
-
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$38,352
Cost:
$67,993
$14,841 261,297 $7,020 1,536 $19,546 9,773 $(-3,055) - $14,841
261,297
kWh
$7,020
1,536
kW-months/year
$19,546
9,773
MMBtu
$(-3,055)
-
$
TOTAL IMPLEMENTED Savings:
$13,280
Cost:
$7,576
$6,936 122,114 $3,281 718 $6,118 3,059 $(-3,055) - $6,936
122,114
kWh
$3,281
718
kW-months/year
$6,118
3,059
MMBtu
$(-3,055)
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $
Electricity Usage Electricity Demand Wood Personnel Changes Electricity Usage Electricity Demand Wood Personnel Changes