Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
28
matching recommendationsNAICS | 221 | Utilities |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UA0244 # 03 Y:2021 | 03 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $54,839 | $180,000 | Not Implemented |
UA0244 # 04 Y:2021 | 04 | 2021 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $283,379 | $2,501,328 | Not Implemented |
UA0244 # 02 Y:2021 | 02 | 2021 | INSTALL OCCUPANCY SENSORS | $893 | $282 | Not Implemented |
UA0244 # 01 Y:2021 | 01 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,477 | $3,209 | Implemented |
UA0244 # 05 Y:2021 | 05 | 2021 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $117,530 | $1,000 | Not Implemented |
UA0238 # 03 Y:2021 | 03 | 2021 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $1,093 | $16,210 | Implemented |
UA0238 # 02 Y:2021 | 02 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,488 | $5,859 | Implemented |
UA0238 # 01 Y:2021 | 01 | 2021 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $161,890 | $279,811 | Implemented |
UA0218 # 04 Y:2019 | 04 | 2019 | OPTIMIZE PLANT POWER FACTOR | $7,816 | $6,955 | Not Implemented |
UA0218 # 03 Y:2019 | 03 | 2019 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $27,441 | $2,000 | Not Implemented |
UA0218 # 02 Y:2019 | 02 | 2019 | INSTALL OCCUPANCY SENSORS | $1,874 | $198 | Implemented |
UA0218 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,378 | $6,360 | Implemented |
UA0208 # 02 Y:2019 | 02 | 2019 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $18,684 | $35,725 | Not Implemented |
UA0208 # 04 Y:2019 | 04 | 2019 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $102,952 | $150 | Not Implemented |
UA0208 # 03 Y:2019 | 03 | 2019 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $26,925 | $150 | Not Implemented |
UA0208 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,648 | $9,245 | Not Implemented |
UA0205 # 05 Y:2019 | 05 | 2019 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $7,670 | $1,600 | Not Implemented |
UA0205 # 04 Y:2019 | 04 | 2019 | MODIFY STARTUP/SHUTDOWN TIMES | $280 | $0 | Implemented |
UA0205 # 03 Y:2019 | 03 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $13,422 | $18,747 | Not Implemented |
UA0205 # 02 Y:2019 | 02 | 2019 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $51,026 | $98,308 | Not Implemented |
UA0205 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $700 | $1,908 | Implemented |
UA0198 # 04 Y:2018 | 04 | 2018 | INSTALL TIMERS AND/OR THERMOSTATS | $2,992 | $180 | Implemented |
UA0198 # 03 Y:2018 | 03 | 2018 | INSTALL TIMERS AND/OR THERMOSTATS | $6,436 | $50 | Implemented |
UA0198 # 02 Y:2018 | 02 | 2018 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,127 | $1,410 | Not Implemented |
UA0198 # 01 Y:2018 | 01 | 2018 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $26,573 | $13,202 | Implemented |