IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

2,275

matching recommendations
Reset
NAICS 221 Utilities
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
CL2010 # 02 Y:2020 02 2020 INSTALL OCCUPANCY SENSORS $1,084 $656 Implemented
CL2010 # 03 Y:2020 03 2020 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $114,467 $157,000 Implemented
CL2010 # 04 Y:2020 04 2020 MODIFY FACILITY TO AVOID EXCESS MAINTENANCE COSTS $14,466 $4,500 Implemented
AS0491 # 01 Y:2020 01 2020 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT $176,974 $3,941 Implemented
AS0491 # 02 Y:2020 02 2020 COMBINE UTILITY METERS $69,299 $735 Not Implemented
AS0491 # 03 Y:2020 03 2020 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $16,587 $9,520 Not Implemented
AS0491 # 04 Y:2020 04 2020 INSTALL OCCUPANCY SENSORS $1,757 $511 Implemented
AS0491 # 05 Y:2020 05 2020 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,511 $2,230 Implemented
AS0491 # 06 Y:2020 06 2020 INSTALL HEAT PIPES / RAISE COOLING SETPOINT $235 $38 Implemented
UF0554 # 01 Y:2020 01 2020 Install Anaerobic Digester $74,732 $250,000 Not Implemented
UF0554 # 02 Y:2020 02 2020 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $19,805 $25,232 Implemented
UF0554 # 03 Y:2020 03 2020 INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS $6,420 $17,086 Implemented
UF0554 # 04 Y:2020 04 2020 LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS $9,363 $0 Implemented
UF0554 # 05 Y:2020 05 2020 INSTALL SENSORS TO DETECT DEFECTS $3,851 $15,420 Implemented
UF0554 # 06 Y:2020 06 2020 USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE $30,206 $6,500 Implemented
UF0554 # 07 Y:2020 07 2020 USE RE-USABLE FILTERS $3,000 $1,906 Implemented
OK1036 # 01 Y:2020 01 2020 INSTALL OCCUPANCY SENSORS $450 $1,163 Implemented
OK1036 # 02 Y:2020 02 2020 USE COUNTER CURRENT RINSING TO REDUCE WASTE WATER $43,157 $12,222 Not Implemented
OK1036 # 03 Y:2020 03 2020 USE RADIANT HEATER FOR SPOT HEATING $1,151 $3,500 Not Implemented
OK1036 # 04 Y:2020 04 2020 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $209 $1,390 Implemented
OK1036 # 05 Y:2020 05 2020 INSTALL TIMERS AND/OR THERMOSTATS $283 $312 Implemented
UF0553 # 01 Y:2020 01 2020 AUTOMATE FINISHING PROCESS $20,196 $46,226 Not Implemented
UF0553 # 02 Y:2020 02 2020 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $6,460 $28,443 Implemented
UF0553 # 03 Y:2020 03 2020 INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS $1,490 $5,608 Implemented
UF0553 # 04 Y:2020 04 2020 DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS $395,494 $1,875,550 Not Implemented