Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
23
matching recommendationsNAICS | 221320 | Sewage Treatment Facilities |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IC0243 # 06 Y:2020 | 06 | 2020 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $130,722 | $713,750 | Implemented |
IC0243 # 05 Y:2020 | 05 | 2020 | SEPARATE TREATMENTS FOR EACH TYPE OF SOLUTION AND RECYCLE | $21,681 | $40,000 | Not Implemented |
IC0243 # 04 Y:2020 | 04 | 2020 | USE OPTIMUM TEMPERATURE | $24,347 | $0 | Not Implemented |
IC0243 # 03 Y:2020 | 03 | 2020 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $21,698 | $6,150 | Implemented |
IC0243 # 02 Y:2020 | 02 | 2020 | USE SOLAR HEAT TO MAKE ELECTRICTY | $37,674 | $140,751 | Implemented |
IC0243 # 01 Y:2020 | 01 | 2020 | USE EXISTING DAM TO GENERATE ELECTRICITY | $1,582 | $31,846 | Not Implemented |
MZ0259 # 04 Y:2018 | 04 | 2018 | RECOVER AND REUSE COOLING WATER | $63,427 | $203,000 | Implemented |
MZ0259 # 03 Y:2018 | 03 | 2018 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $140,488 | $304,000 | Not Implemented |
MZ0259 # 02 Y:2018 | 02 | 2018 | INSTALL OCCUPANCY SENSORS | $504 | $780 | Implemented |
MZ0259 # 01 Y:2018 | 01 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,010 | $29,034 | Implemented |
IC0209 # 02 Y:2018 | 02 | 2018 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,222 | $11,728 | Not Implemented |
IC0209 # 03 Y:2018 | 03 | 2018 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $32,608 | $764 | Not Implemented |
IC0209 # 01 Y:2018 | 01 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,273 | $4,939 | Implemented |
IC0202 # 04 Y:2018 | 04 | 2018 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $8,432 | $34,164 | Not Implemented |
IC0202 # 03 Y:2018 | 03 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,869 | $16,625 | Implemented |
IC0202 # 02 Y:2018 | 02 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,269 | $14,085 | Implemented |
IC0202 # 01 Y:2018 | 01 | 2018 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $86,346 | $283,248 | Implemented |
IC0201 # 01 Y:2018 | 01 | 2018 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $208,328 | $305,915 | Implemented |
IC0201 # 06 Y:2018 | 06 | 2018 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $768 | $0 | Not Implemented |
IC0201 # 05 Y:2018 | 05 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,380 | $422 | Implemented |
IC0201 # 04 Y:2018 | 04 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,551 | $2,023 | Implemented |
IC0201 # 03 Y:2018 | 03 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,439 | $9,545 | Implemented |
IC0201 # 02 Y:2018 | 02 | 2018 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $8,691 | $11,397 | Not Implemented |